3. Setup and Assembly
The Apeks 2000-5L, 20L, 5Lx5L and 20Lx20L systems, chiller and diaphragm compressor come
assembled and require only facility hookup and system interconnect installation.
Leveling Feet
3.1.1.
Use a fork lift or pallet jack to raise the system approximately 6-in off the ground, use
clamps or tie down straps to secure the system to the forks/jack to prevent it from
tipping.
3.1.2.
Insert the supplied leveling feet into the four threaded holes on the bottom of the
extraction system. Ensure that the leveling feet are not threaded into the scale
receiver too far or they will hit the frame and negate scale functionality.
Figure 8. Extraction system leveling feet.
Coolant Connections
3.1.1. Connect the blue cooling line from the outlet of the chiller to the temperature control
coiled heat exchanger on the far left side of the Apeks system as shown below.
Please
note that these lines should not lay on any sharp edges where abrasion can occur.
3.1.2. Connect the blue cooling line from the inlet of the chiller to the top of Separator 2 on the
Apeks system as shown below.
Figure 9. Location and orientation of coolant lines from the chiller to the Apeks system.
3.1.3. Connect the blue cooling line from the top of Extractor (Extractor A on the double
systems) to the oil heat exchanger on the base of diaphragm pump as shown below.
3.1.4. Connect the blue cooling line from the regenerative coiled heat exchanger on the
diaphragm pump to the bottom of the collection cup as shown below.
Summary of Contents for 2000 PSI Series
Page 49: ...Updated 6 16 2016 Copyright Apeks LLC 2014 49 ...
Page 50: ...Updated 6 16 2016 Copyright Apeks LLC 2014 50 Appendix C CO2 Phase Diagram ...
Page 51: ...Updated 6 16 2016 Copyright Apeks LLC 2014 51 ...
Page 52: ...Updated 6 16 2016 Copyright Apeks LLC 2014 52 Appendix D Training Process ...