1.  IDENTIFY BYPASS DAMPER POSITION IN SYSTEM 

Identify where the bypass damper is to be installed.  The bypass damper must be 
located 

downstream

 of any heating or cooling components and 

upstream

 of all 

zone dampers. 
 
The damper may be installed in a horizontal or vertical (upflow) position.  It is 
recommended that the damper be installed horizontally.  The location of the 
damper should allow for clearance around the 
balancing mechanism for free rotation. 
 

2.  INSTALL THE BALANCING 

MECHANISM 

Install the balancing mechanism collar on 
either end of the damper blade shaft and lock 
in place with bolt provided.  Based on the 
damper orientation, move the balancing 
mechanism to the position appropriate for the 
orientation of discharge (see Figure 1).  Lock 
into place with the nut provided. 
 

3.  INSTALL THE DAMPER TO THE DUCTWORK 

  Install the damper with crimped end downstream. 

  For horizontal installation, rotate the damper 

such that the damper blade shaft is parallel to 
the floor and located above the damper 
centerline (see Figure 2). 

  Secure the damper to the duct 

with ½” long, #8 

or #10 sheet metal screws (not included). 

  Insulate the damper.  Leave clearance for free  

rotation of the balancing mechanism. 

 