14
-
AT86M/T-AT88-AT90
English
SLIDING GATES
Preparation for anchoring
2.3
Realise the cement foundation for the plate (template) to
be cemented.
Warning
!
Other assembly methods, with not horizontal motor base,
are forbidden by the manufacturer.
During the inspection in-situ the installer must ensure
there is space enough all around the gate panel suffi cient
for the overall dimensions.
Warning
!
It is essential that the foundation works be carried
out perfectly, following the Fig.3 instructions, in order
to obtain the correc position of the operator and the
electrical cable with respect to the wing gate.
The support base for the operator must be result a few
centimetres above the surrounding ground level.
Excavate a trench (dimensions given in
•
Fig.3
), prepare
2 conduits in fl exible sheaths Ø 30 mm minimum for the
cables.
Fill the
•
trench with good-quality cement.
Position the foundat
•
ion anchors respecting the dimension
A
and secure the plate as described in
Fig.3
.
IMPORTANT!
Meet the Fig.3 dimensions according to the model
installed.
In very snowy zones or areas subject to fl ooding, we
recommend positioning the plate 10-12 cm above the
ground surface.
Check the horizontal position of the plate with a level.
A
350
20
E
BxC
GATE
EDGE
- unscrew nut and washer
- position the unit cabinet
- reposition washer and nut; then
tighten them completely
bolts (D) for
securing the
cabinet
Ø 40 mm holes
for supply lines -
prepare sheaths
in the base plinth.
Gearmotor anchoring
fi g. 3 -
Foundation
plinth
A
B
C
D
E
AT86
MIN
. 40 650
500 M12
65
AT88
MIN
. 40 650
500 M12
75
AT90
MIN
. 50 800
700 M16
80