Commissioning
CAUTION!
The device may only be commissioned by authorized, trained specialists in
accordance with the applicable regulations.
DANGER!
Danger of electric shock!
Protective grounding and electrical connection must be carried out
properly, in accordance with all standards and other applicable national
and international safety rules and regulations for preventing accidents.
7.1
Visual inspection
The device must be visually inspected before commissioning:
-
Correct cable routing, cable shielding
-
Connection of the power supplies
-
Proper connections
-
Secure fit of the screws
7.2
Requirements for commissioning
Before commissioning, the mechanical and electrical installation must be completed. To
commission the devices, the complete structure of the control system must be present
and ready to operate.
After all required components have been connected, the controller unit can be put into
operation.