We recommend a complete overhaul of the unite every 2 years. This operation can only be 
performed by the manufacturer. If necessary, send us your device for maintenance. A complete 
assessment of your device will be made and an estimate of rehabilitation will be sent. 
 
Instructions reminders : 
 
- Use only oil H32 for models CEH or water for models CEO. The guarantees of performance and 
operation are insured with the use of these oils. 
 

> wear are protection : protects the eyes 
against splashes and projections of the 
fluid. 

 
- Don't remove the protective cover. 
 

NOTES : For comparators without isolation valves 

A'

, the capacity of the pumps 60 cm3 may be 

insufficient  to  fully  complete  a  high  volume  measuring  device.  In  this  case,  a  solution  with 
intermediate valve is possible by interposing it between the bench and the device. We repeat the 
cycle as many times as necessary. For these applications, a specific kit can be supplied.  

It can also fill in advance before mounting the pressure generator. 

 

b) Maintenance 

> Valves 

Generator and dead weight are equipped with instrumentation valves, it's imperative to observe 
the following guidelines : 
- Maximum torque applicable abutment valve closed = 4 Nm. 
 

> Tank oil 

Make sure the tank contains enough liquid to make the required calibrations. If necessary, fill the 
tank with the same liquid as that already used. Don't mix different types or brands of fluids into 
the generator and use the recommended oil. 

Skydrol, solvents may damage the o-rings mounted on a generator. 

Keep  clean  bench,  wipe  traces  of  fluid,  and  particularly  the  oil  condition  in  the  tank  to  detect 
traces of pollution. If the fluid in the system is dirty, drain the device and remove dirty oil. 

 

> Option : cleaning kit Ref. OP0025 you 
will aspirate oil durty present in the 
tank. 

 

Don't clean the tank with alcohol 

c) Inspection 

It's recommend to a service of your device every 2 years. The average response time is 2 weeks. 
Cleaning generator, replacement o-rings, testing pressure rise and stability are made. 

 

d) Connection 

The device is equipped with a specific connector for less than 1250 bar pressure. It is necessary 
to orient the ring according to the type of connector correctly. 

Summary of Contents for CEH Series

Page 1: ...ncerns the models model CEH 800B model CEH 1250B model CEO 700B Zone Industrielle Sud Rue Marc Séguin 41100 Vendôme Tel 33 0 2 54 80 79 30 Fax 33 0 2 54 80 79 31 E mail aremeca wanadoo fr site www aremeca instrumentation com Operating Instructions English Modèle fourni N de Série Fabriqué le Contact Commercial d regal aremeca fr ...

Page 2: ...RE ENR 101 Rèv E Le 08 04 2014 page 2 ...

Page 3: ...11 a Pressure generator models CEH or CEO 11 5 Cleaning Maintenance 12 a Cleaning 12 b Maintenance 12 c Inspection 13 d Connectors 13 Threads M10x100 G1 8 1 8 BSP TR 1 8 NPT 13 Threads M12x150 M16x150 M18x150 M20x150 G1 4 G3 8 G1 2 1 4 BSP TR 3 8 BSP TR 1 2 BSP TR 1 4 NPT 3 8 NPT 1 2 NPT 13 6 Annexes 14 Options 14 Read the instructions before handling and retain this information for future use All...

Page 4: ...RE ENR 101 Rèv E Le 08 04 2014 page 4 ...

Page 5: ...CA reserves the right to alter the content or form of this manual at any time and without notice And to make technical amendments to change the product Responsibility AREMECA is not liable for any damage caused by not in accordance with intended usage non compliance with instructions for use use of the instrument by unqualified untrained operator a transformation modification of the device carried...

Page 6: ... use as described in this document In this case of misuse or mishandling outside the technical specifications contained in this manual The instrument must be immediately isolated identified as inoperative and must be checked by our service department Precautions storage and transport It s necessary to take care of the unit during storage or transportation It must be protected from moisture shock e...

Page 7: ...ations commissioning of the instrument performance Personal protective equipment PPE The personal protective equipment must be defined in the security register of the user company and made available to the operator These devices are used to protect the operator from potential risks that impede their safety and health at work Protecting fluid Wear eye protection protects the eyes against splashes a...

Page 8: ...r what is missing b Installation Preferably install your unit in a stable and controlled environment You will get better performance if the temperature and humidity of the room are stable the workstation is clean and dry protected from drafts noise vibration and without passing Component Identification 1 capstan 2 axis de rotation 3 clamping knob 4 connector 5 fastening screw 6 tank 7 valve Instal...

Page 9: ...illing the device with the fluid 1 Open valves 7 and turn the capstan 1 in the direction of clockwise until reaching the stop limit switch forward 2 Remove the filler cap on the tank 3 Fill the 3 4 tank with the correct fluid Don t use other liquids Our devices are mounted and designed to a standard use They function with the fluid provided Some fluids such skydrol castor oil etc are corrosive and...

Page 10: ...see chapter procedure to verify and validate the operational statues of the pressure generator Noted During calibration of instruments with a large volume the amount of fluid in the pressure generator may not be sufficient to achieve the desired pressure in this case the instrument must be filled as much as possible before being connected to the generator to reduce the useful volume of dluid As an...

Page 11: ...lockwise c Close the valve 7 d Turn the capstan 1 in the direction of clockwise until reaching the calibration pressure Maximun operating pressure CEH 800B oil 820 bar CEH 1250B oil 1270 bar CEO 700B water 720 bar e Realize the measurement point Reduce pressure f After the readings measures turn the capstan 1 in the opposite direction clockwise g Open the valve 7 h The instruments can be disassemb...

Page 12: ...he pressure generator b Maintenance Valves Generator and dead weight are equipped with instrumentation valves it s imperative to observe the following guidelines Maximum torque applicable abutment valve closed 4 Nm Tank oil Make sure the tank contains enough liquid to make the required calibrations If necessary fill the tank with the same liquid as that already used Don t mix different types or br...

Page 13: ...able as an option Suitcase with 4 connectors type G Ref OP0171 Suitcase with 4 connectors type NPT Ref OP0172 Suitcase with 4 connectors type BSPTR Ref OP0173 Suitcase with 5 connectors type M Ref OP0174 Suitcase with 17 connectors Ref OP0037 standard o ring Ref OP0038CEO Chap 6 Annexes OPTIONS Oils OP0032 1 liter Oil H32 CEH 800B CEH 1250B Connectors OP0174 Suitcase with 5 connectors metrics M10x...

Page 14: ...h 4 connectors BSPTR 1 8BSPTR 1 4BSPTR 3 8BSPTR 1 2BSPTR OP0037 Suitcase with 17 connectors all connectors Kit cleaning OP0025 Cleaning kit for tank OP0062 Cleaning bench for manometers OP0023 Separator Transport OP0029 Protective cover for economic generator ...

Page 15: ...RE ENR 101 Rèv E Le 08 04 2014 page 15 ...

Reviews: