Chapter 2: Preparation
Tools and Parts Required for Installation
Quick Start Guide: 7000 Series 2 RU Data Center Switches
7
2.2
Tools and Parts Required for Installation
The following tools and equipment are required to install the switch:
Two-Post Rack
•
Screws or rack mounting nuts and bolts.
•
Screwdriver
Four-Post Rack (Toolless)
No additional equipment required.
Accessory kit does not include screws for attaching the switch to the equipment rack. When installing
the switch into an equipment rack with unthreaded post holes, nuts are also required to secure the
switch to the rack posts.
2.3
Electrostatic Discharge (ESD) Precautions
Observe these guidelines to avoid ESD damage when installing or servicing the switch.
•
Assemble or disassemble equipment only in a static-free work area.
•
Use a conductive work surface (such as an anti-static mat) to dissipate static charge.
•
Wear a conductive wrist strap to dissipate static charge accumulation.
•
Minimize handling of assemblies and components.
•
Keep replacement parts in their original static-free packaging.
•
Remove all plastic, foam, vinyl, paper, and other static-generating materials from the work area.
•
Use tools that do not create ESD.
Summary of Contents for DCS-7050SX-128
Page 38: ...36 Quick Start Guide 7000 Series 2 RU Data Center Switches Appendix C Front Panel ...
Page 40: ...38 Quick Start Guide 7000 Series 2 RU Data Center Switches Appendix D Rear Panel ...
Page 44: ...42 Quick Start Guide 7000 Series 2 RU Data Center Switches Appendix F Taiwan RoHS Information ...