Figure 20-1 HC-6100/6300
Figure 20-2 HC-6500/6700
4. Inspect tank drain screen and elements inside the tank. The elements should appear to be flaking
off scale. If the drain screen appears to building deposits in the screen holes it should be cleaned.
Remove any scale that appears in the bottom of the tank.
5. Install six (6) new ionic beds (14 for the HC-6500/6700), snapping them into place on the
support pins.
6. Make sure access panel gasket is lapped over all edges of tank access opening. Replace and
secure tank access panel.
7. Make sure both access doors/panels are secure.
8. Turn on power at circuit breaker.
20
Steam Outlet
Equalizing Connection
to Top of Level Canister
Cover
Ionic Beds
Equalizing Connection
to Bottom of Level Canister
Heating
Elements
Drain Oulet
Connection
Locating
Pins
Mounting Bolt
Locations
Cover
Ionic Beds
Heating
Elements
Drain Outlet
Connection
Mounting Bolt
Locations
Locating
Pins
Equalizing Connection
to Bottom of Level Canister
Equalizing Connection
to Top of Canister
Steam Outet
Summary of Contents for HumidiClean HC-6100 Series
Page 28: ...HC6100 Wye Wiring layout 28...
Page 29: ...HC6100 Delta Wiring layout 29...
Page 30: ...30 HC6100 PAR Single Phase Wiring Layout...
Page 31: ...HC6300 Wye Wiring layout 31...
Page 32: ...HC6300 Delta Wiring layout 32...
Page 33: ...HC6500 Wye Wiring layout 33...
Page 34: ...HC6500 Delta Wiring layout 34...
Page 35: ...35 HC6500 WYE 2 contactors Wiring Layout...
Page 36: ...36 HC6500 Delta 2 contactors Wiring Layout...
Page 37: ...HC6700 Wye Wiring layout 37...