background image

SH-2000, SH-2500, AB-3000

Bimetallic Steam Traps

Installation and Operation Manual 

65

SH-2500

SH-2000

AB-3000

Summary of Contents for SH-2000

Page 1: ...SH 2000 SH 2500 AB 3000 Bimetallic Steam Traps Installation and Operation Manual 65 SH 2500 SH 2000 AB 3000...

Page 2: ...ld be used by qualified personnel as a guide to the installation of Armstrong SH 2000 SH 2500 And AB 3000 Bimetallic Steam Traps Selection or installation of equipment should always be accompanied by...

Page 3: ...itical from both a performance and maintenance aspect Installation of the trap is simplified if you follow these guidelines 1 Before installing the trap ensure the line is clean Blow down any strainer...

Page 4: ...valves upstream and downstream of the trap Refer to figures 4 1 and 4 2 IS2 The IS2 connector block should be installed in piping with the flow direction stamp pointing in the correct direction as ind...

Page 5: ...nnector block after the connector block has been installed When installing the trap to the connector block apply 35 50 ft lbs of torque to the bolts using a 9 16 wrench Allow 2 5 clearance for bolt in...

Page 6: ...c Pipe line or elbows plugged d Pressure reducing valve out of order e Isolation valves are off closed Caution Superheated steam is invisible Do not place objects directly in the path of trap discharg...

Page 7: ...l need to be installed AB 3000 Remove the steam trap from the connector block by taking the two bolts out Unscrew and lift the cap Unscrew and replace the bimetallic element The distance between the f...

Page 8: ...he products supplied by Armstrong however caused and whether such claim is based upon warranty contract negligence strict liability or any other basis or theory is limited to Armstrong s repair or rep...