Operation
ASCO Model K875A Outdoor Load Bank
4-3
9.
The resistive loading is selected by toggle switches, using any one or combination of
the toggle switches to make up a given load.
10.
By placing the MASTER LOAD switch to the ON position, the preselected load will be
applied to the power source.
11.
Any load switch can be added or removed as required while the MASTER LOAD switch is
closed (ON).
12.
To remove the load, open the MASTER LOAD switch by placing it in the OFF position.
SHUTDOWN
1.
Place the MASTER LOAD switch to the OFF position.
NOTE
After running a load test, residual heat may be removed from the
Load Bank by allowing the blower to operate for a few minutes after
loads are removed. This procedure is not required for maintaining
Load Bank integrity, but it may guard operating personnel from
possible burn injuries.
2.
Place the control power ON/OFF switch to the OFF position, and other switches on the
control panel should be turned OFF.
3.
Shut down the power source/sources.
4.
Disconnect the Load Bank from the power sources.
AUTOMATIC OPERATION (for K875A Load Banks with Load Shedder option)
1.
Place all switches on the control panel to the OFF position.
2.
Connect the generator or other power source to be tested to the Load Bank as described in
the INSTALLATION section.
3.
Place the POWER switch to the ON position. The CONTROL POWER light (DS1) will be
energized, indicating control power is present.