5 - Installation
Astra’s bathtubs are tested one by one,
which makes sure that they are perfectly
functional. However, we recommend that the
customer make a test before the installation in
order to detect any eventual leak in the hydraulic
part as damages may occur during transport.
PRE-INSTALLATION
TEST
TO
CHECK
POSSIBLE LEAKS:
5.1 - Local preparation
a - Underlay the bathtub so as to level it.
b - Check the spot and water pump voltage.
c - Plug the water pump into the bathtub.
d - Fill the bathtub with water until the jets are
covered (the bathtub must not be switched
on empty).
e - Switch on the water pump and check if there
is any leak.
f - If there is any, contact your supplier.
1
Inspection door
sewage line
Ø 40mm
Handles
(in case of
central water
heater)
300mm
Do not align water inlet with bathtub water
inlet or sewage line with outlet line. Connections
of those points with the bathtub must be done
with adequate tubes and connections.
The floor and wall of the place where the
bathtub will be installed must be waterproofed.
Let the water inlet point, electric points, and
sewage outlet point ready on installation site
and according to dimensions of bathtub on
Picture 1. Bathtub dimensions can be found on
Astra website or at the end of this manual.
Summary of Contents for Classic H34
Page 1: ...1 BANHEIRAS MANUAL DE INSTALAÇÃO BAÑERAS Manual de Instalación BATH TUBS Installation Manual ...
Page 2: ...2 ...
Page 45: ...45 ...
Page 47: ...47 ...