4.2   Grounding 

 

(n) Grounding the aluminum frame with copper wire 

4.2.1  The  grounding  requirements  must  be  checked  in  accordance  with  the  applicable 

regulations and standards before work is started. 

4.2.2  Use the marked 5.5 mm grounding holes to ground the anodized frame. Use one M5 nut, 

two M5 cut washers, one M5 plain washer, one M5 spring washer, and one M5 bolt and 
the  copper  wire.  All  nuts,  bolts,  and  washers  are  type  M5  and  should  be  made  of 
stainless steel (Fig. (n) ). 

4.2.3  Put the bolt through the cup washer and wrap the copper wire around the bolt. (Note that 

the copper wire cannot be attached directly to the aluminum.) 

4.2.4  Put the bolt through the cut washer and then through the hole in the aluminum frame. 
4.2.5  Add the spring washer and nut on the other side of the bolt and tighten to secure all parts. 

The tightening torque should be 210±20 N•cm. 

4.2.6  Approve  the use  of  UL-467  certified  bonding  and  grounding  devices,  including  Burndy 

(formerly Wiley Electronics) Washer Electrical Equipment Bonding (WEEB) and similar 
devices, such as barbed washers, that meet the requirements of UL-467 as suitable for 
electrical bonding and grounding PV modules to PV mounting systems. 

4.2.7  Other grounding methods may be allowable when tested with the racking system per 

UL 2703 requirements.   

 

5  Maintenance 

5.1    Regularly carry out a visual inspection for dirt, dust, bird dropping, leaves, and other detritus 

covering the modules. 

Summary of Contents for CHSM60M(DG)/F-B

Page 1: ...nt com Crystalline Silicon PV Module Installation Manual 1 Introduction 1 1 Purpose 1 2 Limitation of Liability 1 3 Precautions for Installation 2 Safety 2 1 General Safety 2 2 Installation Safety 3 M...

Page 2: ...ense arising out of or in any way connected with such installation operation use or maintenance Chint Solar reserves the right to change the manual without prior notice 1 3 Precautions of Installation...

Page 3: ...ooftop the number of each stack is suggested no more than 20 In case of the poor load bearing capacity it s recommended that the designer and or installer check with the structural engineer or archite...

Page 4: ...e modules 2 1 10 Do not scratch or hit at the back sheet the glass the terminal box Do not pull the cables or touch them with bare hands 2 1 11 Do not drill holes in the frame or scratch the anodized...

Page 5: ...t the mounting surface touching the junction box 2 2 17 Standing on the solar PV module is forbidden and also prohibit installation tools or other objects hitting surface of the solar PV module 2 2 18...

Page 6: ...s available as shown in figure 3 While installing the module frame should be parallel to the mounting rack to avoid casting shadow on the rear side as shown in figure 4 Figure 1 Figure 2 Figure 3 Figu...

Page 7: ...Tel 0086 571 5603 1888 Fax 086 571 5603 2316 Website http energy chint com Figure 5 3 2 2 Clamping on the frame surface 3 2 2 1 Double glass module During the installation of bifacial modules the fram...

Page 8: ...e added for additional support 3 As for above figure 7 indicates the allowable installation range of the aluminum clamp the recommended installation location is 50 200mm For this installation the modu...

Page 9: ...omponents b The bar s top surface contacted with module frame should come with grooves compatible with an M8 bolt c If the bars do not come with grooves holes of a suitable diameter may need to be dri...

Page 10: ...roduce more current and or voltage than reported at standard test conditions Accordingly the value of Isc marked on this module should be multiplied by a factor of 1 25 when determining component cond...

Page 11: ...wire around the bolt Note that the copper wire cannot be attached directly to the aluminum 4 2 4 Put the bolt through the cut washer and then through the hole in the aluminum frame 4 2 5 Add the spri...

Page 12: ...th Dust weather Right away after the dust wind The period of the PV module cleaning shall be determined by the condition of the weather pollution O M operator shall keep a record of weather condition...

Page 13: ...g District Hangzhou P C 310053 Tel 0086 571 5603 1888 Fax 086 571 5603 2316 Website http energy chint com CHINT SOLAR ZHEJIANG Co Ltd Add 1335 Bin an Rd Binjiang District Hangzhou China 310053 Tel 86...

Reviews: