6.2.15
Electrical insulation monitoring device operation test
With the frequency indicated in the general chart, check the operation of the
device that monitors the electrical insulation of the 220V power supply of the
inverter (only if present).
The test must be performed with the internal combustion engine on, selector 6
on the console must be in the "OUT 220 V" position. In fact, this enables 220 V
voltage to be supplied to the outlet on the work platform.
At this point, it is necessary to simulate a dispersion by making a bridge with a
cable between the outlet on the work platform and a grounding point of the
machine.
This simulates an abnormal situation and automatic voltage release by the
device. When the device is released, an warning buzzer located on the electrical
panel will emit a steady sound, which will remain active until the operator
reactivates the breaking device.
WARNING: IN THIS CONFIGURATION, THE OUTLET ON THE WORK PLATFORM IS
POWERED; THEREFORE HIGH VOLTAGE IS PRESENT. THIS OPERATION MUST BE
PERFORMED ONLY BY QUALIFIED TECHNICIANS.
Summary of Contents for 1470-HE EVO
Page 7: ...PAGE 7...
Page 12: ...PAGE 12 Work area on tracks Travel not allowed Maximum inclination allowed 2 5020 5490 7500...
Page 27: ...PAGE 27...
Page 28: ...PAGE 28...
Page 34: ...PAGE 34 Warning Do not tighten the fixing belts too much so as not to damage the eye bolts...
Page 50: ...PAGE 50 8 Extendible basket pedal...
Page 57: ...PAGE 57 38 Chassis and stabilisers...
Page 74: ...PAGE 74...
Page 76: ...PAGE 76...
Page 77: ...PAGE 77...
Page 80: ...PAGE 80...
Page 138: ...PAGE 138...
Page 160: ...PAGE 160...
Page 161: ...PAGE 161...
Page 162: ...PAGE 162...
Page 163: ...PAGE 163...
Page 164: ...PAGE 164...
Page 165: ...PAGE 165...
Page 166: ...PAGE 166...
Page 167: ...PAGE 167...
Page 168: ...PAGE 168...
Page 178: ...PAGE 178 MANDATORY ROUTINE INSPECTIONS Date Observations Seal Signature...
Page 191: ...PAGE 191 8 4 Hydraulic diagram See attachment 8 5 Wiring diagram See attachment...