77
Instruction book
9096 3313 00
4.3 Putting into operation (commissioning)
1. Verify that the OSCi drain valves (4) are closed.
2. Unscrew the clamping ring (1) of the cover of the first vessel of the OSCi and take off the cover (2).
3. Take out the CDROM and the box (3) with the test bottle and the reference bottle and keep them in a
safe place nearby the compressor.
4. Take the ISO 7-R ½ connection and the G ¼ ball valve with seal and screw them into the corres
ponding threads in the drain plate at the bottom left of the compressor front panel (Drain plate). Close
the condensate sample valve.
Summary of Contents for GA 55+
Page 1: ...GA 55 GA 75 GA 90 Instruction book Atlas Copco Oil injected rotary screw compressors ...
Page 2: ......
Page 4: ......
Page 9: ......
Page 96: ...96 Instruction book 9096331300 6 Installation 6 1 Dimension drawings Centre of gravity ...
Page 98: ...98 Instruction book 9096331300 6 2 Installation proposal Compressor room example ...
Page 109: ...109 Instruction book 9096331300 ...
Page 123: ...123 Instruction book 9096331300 Procedure Oil system components Oil drain plugs ...
Page 145: ...145 Instruction book 9096331300 Notes ...
Page 146: ...146 Instruction book 9096331300 Notes ...
Page 147: ...147 Instruction book 9096331300 Notes ...
Page 148: ......
Page 149: ......