Procedure
Step
Action
1
Open the air outlet valve (customer's installation).
2
Switch on the voltage and check that voltage on sign (5) lights up.
3
Press start button (7). The compressor starts running in unloaded condition and
operation sign (4) lights up.
4
Approx. 25 seconds later (programmable), the compressor starts running loaded.
5
Regulate the water flow with the compressor running loaded. The aim is to obtain a
cooling water temperature rise over the complete compressor unit of 15 K.
See section
for the cooling water temperature.
See section
for the cooling water consumption.
If the motor is stopped and operation sign (4) is alight, the motor may start
automatically.
If the start/stop timer is active, the compressor can start automatically, even if it was
stopped manually.
Instruction book
82
AIF999999
Summary of Contents for ZR 200
Page 1: ...Instruction book AIF999999 ZR 200 ...
Page 2: ......
Page 61: ... CORRECT installation Instruction book AIF999999 59 ...
Page 108: ......
Page 109: ......