Additional Information
51
Apex-10 / Apex-10H
Additional Information
Final Check of Assembled Lift
Final dimension check after anchoring.
Base and columns properly shimmed and stable.
Anchor bolts tightened.
Runways properly attached, secured, and level.
Check for hydraulic leaks.
Ensure cables are properly routed and free from obstructions.
Check jam nuts on cables are tightened.
Check oil level and look for leaks.
Check adjustment of safety release cable to ensure both sides
are working properly.
Re-check level of towers.
Check torque of anchor bolts.
Check all fasteners, tighten if necessary.
Electric power supply confi rmed.
Check for overhead obstructions.
Check shut off at top of stroke to ensure lift shuts off.
Check proper operation of arm restraints.
Operate lift to full stroke then lower to ground while checking for
proper functionality.
Check proper operation of arm restraints.
Operation and Safety Manual at site.
Ensure all documents listed below are given to the owner.
ANSI / ALI Lift It Right Manual.
ANSI / ALI Safety Tip Card.
ANSI / ALI ALIS Safety Requirements for Installation.
ALI/LP Lifting Points Quick Reference Guide.
Train end user on operation of lift.
Summary of Contents for APEX-10
Page 1: ......
Page 19: ...Technical Specification 19 Apex 10 Apex 10H Figure 3a Standard Version...
Page 20: ...Technical Specification 20 Apex 10 Apex 10H Figure 3b Taller Version...
Page 23: ...Technical Specification 23 Apex 10 Apex 10H Figure 6 Electrical Diagram 220V 60Hz 1PH...
Page 26: ...Safety 26 Apex 10 Apex 10H...
Page 27: ...Safety 27 Apex 10 Apex 10H...
Page 30: ...Installation 30 Apex 10 Apex 10H Figure 8a Floor Plan...
Page 61: ...Parts Catalogue 61 Apex 10 Apex 10H Parts Catalogue ED 01 2015...