Maintenance
35
PV-15P
9.2 Periodic
Maintenance
Daily pre-operation
• Check hydraulic connections and hoses for leaks
• Check mechanical locks audibly and visually while in
operation
• Check arm locks
• Check bolts, nuts and screws are tight
Every 1 month
• Check all cable connections, pins and bolts to insure
proper mounting
• Inspect all anchor bolts and retighten if necessary
• Check columns for square-ness and plumb
• Check equalizer cable tension, adjust if necessary
• Check safety cable, adjust it if necessary
• Check all arm pivot pins. Make sure they are
properly secured
• Check all lifting pads, replace if necessary
• Lubricant columns with grease
• Check the hydraulic oil, fi ll or replace if necessary
• Check hydraulic systems for proper operation
Every 12 months
• Verify that all components and mechanisms are not
damaged
• Verify the equalizer cables are not worn, change if
necessary
• Check the electrical system to verify that the motors
operate properly (this work must be carried out by
skilled electricians)
• Empty the oil tank and change the hydraulic oil