Atmos Heating Systems
23
•
Drill a 60mm hole in the roof
•
Fit the compression elbows to the pipes coming out at the rear of the header.
•
Connect the red and blue collector pipes.
•
Take the red and blue collector tubes and the sensor cable through the pipe gland to
the storage tank.
•
Ensure that
AT ALL POINTS THE PIPES SLOPE DOWN
away from the collector
header and also ensure that there is enough slack in the pipes for thermal contraction
(max 5%).
•
Fix and seal the pipe gland to the roof using roof sealant.
•
Fit insulation to the red collector tube along the whole of its length and to the blue
collector tube only above roof level.
•
The pipes must be fixed sufficiently to prevent excessive movement on
occasions of strong wind.