background image

 

1.  Remove roofing tiles in the area of solar panel assembly (upper edge of the collector panels 

approx 3 to 4 rows of tiles from the ridge). 

2.  Fasten the supporting profile to the rafters using wood screws, 80 to 100mm above the 

lathwork. Pay attention to weathering of the profile, in respect to the position of the panel. 

3.  Attach hooks to the supporting profile according to the picture shown. Do not tighten the 

screws as further adjustment will be necessary. 

4.  Attach the supporting G-profile to the lower hooks, as shown in the picture. For 3 panels, 

set up the G-profiles using 330mm connecting piece. 

5.  To the upper hooks, attach the U-profile in line with the supporting G-profile of the lower 

side. For 3 panels, set up the two U-profiles using L-connector and self tapping screws. 

6.  Tighten all screw connections. 
7.  After drilling the holes for the solar panels pipework, replace the roofing tiles. 
8.  Position the solar panels as shown in the picture, using packing as required to space the 

panels 22mm apart. Tighten the screw connections. 

NOTE: 

The panels should be connected as shown in section 6. The compensator (for 

expansion) is within the panel and has stainless steel pipe with male connector. 

9.  Using the self-tapping screws, secure the solar panels to the U profile. Be careful not to 

strip the thread. 

10. Check the seating of the parts and the tightness of all the pipe joints. 

 

Quantity Description 

pan 

pan 

 

2000mm Supporting profile 

 

1500mm Supporting profile 

6 8 

Bearing 

hook 

6 8 

Fastener 

1 1 

2215mm 

G-profile 

 1 

1115mm 

G-profile 

1 1 

2215mm 

U-profile 

 1 

1115mm 

U-profile 

12 

16 

8 x 50mm screw 

12 

16 

6 x 20mm screw 

5.5 x 16mm A2 self tapping screw 

8 x 80mm wood screw 

12 16 

M8 

Nuts/washers 

12 16 

M6 

Nuts/washers 

 

330mm connecting piece C (Zn) 

 

300mm connecting piece L (AlMgSi) 

24mm diameter packing 

 

4.0 

Installing Solar Panels on Flat Roofs 

Solar panels may be installed on flat roofs using a separate A-frame. Contact Atmos for more 
details. 
 

5.0 

Installing the System, Operation and Maintenance 

5.1 Basic 

Guidelines 

See the System and Control diagrams 

1.  Compression fittings suitable for the application can be used. 
2.  Solar circuit pipes must be insulated with high temperature insulation (eg Armaflex). 
3.  The power cable must be run to the BS3 controller (via a wiring centre or junction box if 

using an unvented tank) from a 230 volt, 5 amp fused, earthed electrical supply.  

4.  The collector and tank sensors are supplied with the BS3 controller.  
5.  The solar circuit must be plumbed to the tank lower coil and the tank sensor S2 (using 

heat conductive paste) fitted into the sensor pocket. 
 
 

Twin Coil Sealed Solar System Ins Man  

 

                           Page 6 of 15 

Summary of Contents for Twin Coil Sealed Solar System

Page 1: ...allation User Manual THIS MANUAL IS TO BE LEFT WITH THE HOUSEHOLDER AFTER INSTALLATION Atmos Heating Systems West March Daventry Northants NN11 4SA Tel 01327 871990 Fax 01327 871905 e mail sales atmos uk com internet www atmos uk com T2 panels enlarged Appendix Issue 3 12 07 ...

Page 2: ...Twin Coil Sealed Solar System Ins Man Page 2 of 15 ...

Page 3: ... in the centre of the roof 1 2 2 The minimum angle of the roof and therefore the solar panel should be 30 degrees The maximum height of the solar panel should normally be 10 metres 1 2 3 Ensure that there will be enough space to fit the solar panel Because of the flashing in the case of roof integrated panels it is best to have at least one column of tiles between the panel and a vertical edge and...

Page 4: ...stalling Roof Integrated Solar Panels For pantiles etc but not slates See separate leaflet available from Atmos 3 0 Installing On Roof Solar Panels 2 Panels Twin Coil Sealed Solar System Ins Man Page 4 of 15 ...

Page 5: ...3 Panels Twin Coil Sealed Solar System Ins Man Page 5 of 15 ...

Page 6: ... secure the solar panels to the U profile Be careful not to strip the thread 10 Check the seating of the parts and the tightness of all the pipe joints Quantity Description 2 pan 3 pan 2 2 2000mm Supporting profile 2 1500mm Supporting profile 6 8 Bearing hook 6 8 Fastener 1 1 2215mm G profile 1 1115mm G profile 1 1 2215mm U profile 1 1115mm U profile 12 16 8 x 50mm screw 12 16 6 x 20mm screw 4 6 5...

Page 7: ... than the given channel DTO The solar pump is switched off when the difference in temperature between S1 and S2 is smaller than the given channel DTF If the temperature rises above the maximum storage temperature channel SMX the solar pump switches off If a temperature of above 140 C factory setting but adjustable channel EM at the controller is reached at the solar panel sensor the solar pump is ...

Page 8: ...n Mineral wool 66 mm thick Side insulation Mineral wool 20 mm thick Connection G3 flat packing Absorber All copper absorber with highly selective surface Absorption 95 2 Emissivity 5 Working pressure 2 4 Bar Content 1 1 Litre Efficiency Certification by an independent testing laboratory ISE Freiburg EN 12975 1 2 Maximum efficiency η0 0 77 77 Stagnation temperature no load operation 202 C Other inf...

Page 9: ...nk 240 volt switched supply Atmos Heating Systems Installation diagram for Twin coil tank with Single station pump set BS 3 controller KEY 1 Integrated compensator within panel has stainless steel pipe with male connection flexi connector 2 inch brass end cap with washers 3 22mm inch MI compression elbow with washers 4 a Connect inch brass nipple in one end of inch brass tee b Connect x inch brass...

Page 10: ...hermostat and remove the control thermostat part so that just the 85 deg C limit thermostat is left Fit the tank sensor using heat conductive paste and the limit thermostat into the lower pocket double segment and bring the sensor cable out through the thermostat spare gland 3 Keep sensor cables separate apart from other cables 4 An additional sensor S3 can be fitted into the pocket near the top o...

Page 11: ...s shown in the Appendix 10 Equipotential bonding is refitted 11 Pump speed set to the highest 12 Solar panel system has been filled with anti freeze anti corrosion fluid 13 De aeration valves manually bled 14 Solar panel system pressurised at 3 to 4 bar 15 Solar system controller operation checked and the controller left in AUTO 16 The pump unit is fixed securely and not vibrating or noisy Pump op...

Page 12: ...Hot water out to taps Terminal box Immersion heater Unvented tank expansion vessel white as supplied with tank Connect to cold water inlet assembly with braided hose Flow and return to radiators Flow Return Room thermostat Thermostat for boiler control Pocket for solar sensor S3 optional Gas supply Secondary hot water return blank off if not required Electrical connection All connections are 240 v...

Page 13: ...7 3 Controls Diagram for RCM Unvented Twin Coil tank with HE26 Boiler Note Diagram shows Salus controls Twin Coil Sealed Solar System Ins Man Page 13 of 15 ...

Page 14: ...ostat for boiler control Pocket for solar sensor S3 optional P T valve to tundish and discharge Commissioning valve and Secondary hot water return if required Two port motorised valves Time clock programmer Flow and return to radiators Cold inlet with valve assembly as supplied with tank Atmos InterSystem HE26 condensing gas boiler Note Tank is OSO unvented tank with internal secondary expansion N...

Page 15: ...7 5 Controls Diagram for OSO Unvented Twin Coil tank with HE26 Boiler Note Diagram shows Salus controls Twin Coil Sealed Solar System Ins Man Page 15 of 15 ...

Reviews: