Step 2 Remove the Data Logger
Covers
Remove the screws and the front cover of the
Data Logger. Then remove the screws and
blue AC terminal cover .
Step
3 Data Logger Terminations
AC Power Termination(1-Phase)
For 1-phase AC applications, feed cable
through the bottom left opening of Data Logger
housing and the rubber grommet to reach the
AC terminal. Connect the L1 terminal to the
“Hot”(black) wire of
split-phase
system and, the
N terminal to the neutral(white) wire.
Do not
exceed NEC 20A and 17 module branch circuit
protection limit.
Ethernet Termination(RJ45)
Use T568B to terminate the CATV+ ethernet
patch cable to connect the network socket to a
10/100Base-T router or broadband gateway.
Before terminating your RJ45, please note the
following standard T568B pin out and color code
sequence. *
It is always a good idea to validate or
test your RJ45 terminations with standard
network cable testing equipment.
*
For best results please hardwire the Data Logger to the PV Distribution Panel.
Please do not ground or bond the Data Logger
Summary of Contents for AC UNISON
Page 7: ...AUO AC Unison AUO AC Unison Installation Guide Page 6 of 44 February 2012 Rev 1 0 ...
Page 10: ...AUO AC Unison AUO AC Unison Installation Guide Page 9 of 44 February 2012 Rev 1 0 ...
Page 11: ...AUO AC Unison AUO AC Unison Installation Guide Page 10 of 44 February 2012 Rev 1 0 ...
Page 12: ...AUO AC Unison AUO AC Unison Installation Guide Page 11 of 44 February 2012 Rev 1 0 ...
Page 39: ...AUO AC Unison AUO AC Unison Installation Guide Page 38 of 44 February 2012 Rev 1 0 ...