- American National Standards Institute and Electronic Industries Association
standard ANSI/EIA-310–D-92.
- International Electrotechnical Commission standard IEC 297
- Deutsche Industrie Norm standard DIN 41494
• Screws that come with the racks for installing the rails
• #2 cross-point (Phillips) screwdriver or 3/8 inch flathead screwdriver
• USB keyboard, USB mouse, and monitor must be available on the site for advanced
installation or troubleshooting.
• Power from a nonswitched electrical outlet
• Access to the network
Clearance requirements
Install the server in a rack that meets the following requirements:
• Minimum depth of 70 mm (2.76 inches) between the front mounting flange and inside of
the front door if the server is installed in a cabinet.
• Minimum depth of 157 mm (6.18 inches) between the rear mounting flange and inside of
the rear door if the server is installed in a cabinet.
• Minimum depth of 718 mm (28.27 inches) and maximum depth of 762 mm (30 inches)
between the front and rear mounting flanges to support the use of the cable-
management arm.
Server installation checklist
No.
Task
Notes
1
Verify that all equipment is on
site.
Compare the list of items that were ordered
to the contents of the boxes. Use the
inventory list provided by your project
manager. Do not rely on the packing slips
inside the boxes for the correct information.
2
Verify that the rack is installed
according to the manufacturer's
instructions and in accordance
with all local codes and laws.
Clearance requirements
Installing the Avaya S8800 Server for Avaya Aura
™
Communication Manager
June 2010 15