Battery Cabinet Installation
20
Avaya
t
RS9 UPS (9–18 kVA, 9-Slot Models) Site Preparation, Installation and Operator’s Manual
S
164201543 Rev A
Entrance Panel
Battery Cable
Connection
Point
Figure 13. UPS Power Entrance Panel
3.
Verify all hazardous voltages have been removed from the
backplane by testing with a voltmeter or other test device.
4.
Feed one end of all three battery cables through the strain-relief
clamp located on the cable assembly’s entry plate (see
Figure 14).
5.
Secure each battery cable to the cable assembly as shown in
Figure 14. Torque all nuts to 75–85 in lb (8.5–9.6 Nm).
6.
If the battery cable will be installed in customer-supplied
flexible or other conduit (as required by local wiring codes),
loosen the two screws holding the strain-relief clamp shown in
Figure 14. Remove the clamp by loosening the star nut on the
inside of the entry plate, leaving the nut in place. Replace the
clamp with a panel-to-conduit feedthrough and secure it with
the star nut.