Mooney M20 series
Installation Instructions
AVE-MOD-012-INS
Issue 02
__________________________________________________________________________________
Aveo Engineering Group
, s.r.o.
Drasov 202, 261 01 Drasov
Czech Republic
Issue of form 01
Page 14 of 21
Figure
and
Index
Number
Part Number
Description
Parts
Avail.
QTY.
Per
assy.
1
2
3
-------
24
25
26
27
28
29
30
31
32
33
34
35
AVE-PSPSYW-T01
MS-16995-19
AVS-P000105638-A10
----------------------------
Original parts
Several
470004-003
470004-005
A6-120
Several
Several
Several
Several
Several
Several
Several
1-480305
470011-001
PosiStrobe Titania
Screw #6-32 Thread, 5/8“ SHCS
Gasket
------------------------------------------------
Ring
Plate
Rivet Nut
Nav light / Strobe light assy
Screw 6-32
Retainer
Lens
Gasket
Bulb
Base assembly
Connector
Shield
------
1
2
1
-----
1
1
2
1
2
1
1
1
1
1
1
1
NOTES
1.
Remove position light in accordance to the aircraft maintenance manual.
2.
Disconnect the wire bundle from the position light
3.
Inspect the installation area for corrosion and correct according to AMM if
required
4.
Splice the new light’s wires into the existing connector according to the
referenced installation manuals and the common practice FAR AC 43.13-2B
Chapter 4
5.
In case strobe light and synchronization wire are to be added then run two wires
with minimum wire gage 22 parallel to the position light wire bundle. The wires
are to be connected to the corresponding wires of the wing tip lights. The strobe
light might also be operated together with the position light due to low power
consumption or both functions may not be used (just not connected).
6.
Install items 1, 2, 3 as described.
7.
After installation of the light balance the ruder according to AMM chapter 27-93-
01