A-Series Dobby Loom Assembly Manual
Install the Inner Workings
Attaching the Harness Cables
Page | 51
4)
Route the longer cable over the far pulley on the left side of the
loom and let it hang.
Figure 57 - Harness cables hanging on loom
5)
Repeat this procedure with each of the remaining cables until all of
the harness cables are over all of the pulleys.
6)
After all cables are in place on each pulley, check to see that no
cables have crossed over each other.
7)
Replace the cable retainer above the right set of pulleys, tightening
the screws so that it almost touches the pulleys.
Note:
It is essential to the proper functioning of the loom that the cables be free to
move. The cable retainer’s purpose is to keep the cables from jumping off of
their pulleys.
8)
Replace and tighten the left cable retainer as you did the right one.