8
INSTALLATION
Installing the Blower Unit
• Install the Blower Unit onto steady lumbers in the
attic.
• Connect the duct work from the Hood Unit to the
bottom vent opening of the Blower Unit and seal
the connection.
• Connect the duct work from the Roof/Wall Cap to
the top vent opening of the Blower Unit and seal
the connection.
• Connect the wires:
• If you have purchased the Awoco Split Hood
Unit or the Control Unit
• Refer to Step 1a in Page 5 to connect the
wires. Install the Control Unit on the wall or
other suitable places.
• If you didn't purchase the Awoco Split Hood
Unit or the Control Unit and want to set the
Blower Unit at 1 speed only
• Refer to Step 1b in Page 6 to connect the
wires.
• If you want to use your existing range hood
control panel to control the Blower Unit
• Refer to Step 1c in Page 7 to connect the
wires.
• Insulate the connected wires and any unused wires.
• Plug in the Power Cords and test run again to
confirm all buttons are working properly. Refer to
Page 10 for troubleshooting.
Connection
Box
Vent out to the
Roof/Wall
Vent in from the
Hood Unit
Vent in from the Hood Unit
Vent out to the Roof/Wall
Blower Unit Installed Vertically
Blower Unit Installed Horizontally
Note: If mounting the 6" Blower Unit
horizontally, please remove the built-in
damper first, then install an air damper
at the roof/wall vent out.