3.3.4
Subsequent installation of additional battery modules
1.
check the voltage of the modules. This should be between 46 V and 56 V.
2.
adjust the voltage of the battery system to ±1 V for the new modules (see also Appendix
8.3: Adjusting the system voltage with SMA SB Storage). An exactly adjusted module
voltage avoids system voltage adjustment and allows immediate access to the
entire capacity.
3.
disconnect the inverter and switch off Hyperion.
4.
Install new modules. See chapter 3.3 Installation.
5.
put the system into operation. See chapter 3.4.
3.3.5
Disposal measures
Dispose of transport packaging for recycling in accordance with the statutory provisions.
It is recommended to keep not required parts (patch cables, dummy plugs, screws) together with the
installation instructions near the battery system.
Before removing defective Energypacks, the power socket must be taped with insulating tape after
removing the power plug.