Step 12: Pole End Assembly
Parts needed
2-Batting Bar Bracket Assembly
2-Batting Bar Bracket Clamp
8- M6x25mm Socketed Washer Head Cap Screw
QF05300-113
Tools Required
M4 Allen Wrench (provided)
12-1: NOTE: This step includes a
recommendation for the position of the
batting bar bracket. This position can be
changed, depending on the diameter of
the batting roll and the frame-height.
Position the batting bar bracket assembly
on the outside of the front end leg, as
shown in
Fig. 12-1
. The bracket is installed
approximately in the center of the upper end
leg. Ensure that both brackets are set at the
same height. The clamp has a cutout for the
front end-leg height-fixing screw,
Fig 12-1
.
The front end-leg height-fixing screw will need
to be either inside the cutout or above or below
the clamp.
12-2:
Insert the four (4) M6x25mm QF05300-
113 through the batting bar bracket assembly
and into the weld nuts on the clamp. Adjust to
the desired height and tighten the screws until
the clamp remains fixed at the desired height.
Do not over-tighten the clamp.
Step 12
Batting Bar Bracket Assembly
Fig. 12-1
Initial height set
approximately at
center of upper leg.
Cutout
for
height
fixing
screw.
12-3:
Repeat
Step 12-1 and Step 12-2
to install the remaining batting bar bracket
at the other end of the frame. Be sure to set
the batting bar bracket assembly to the same
height on both sides.