WWW.BALTIMOREAIRCOIL.COM
6
Figure 6.
Coil Casing/Lower Section Bolt Assembly
Figure 5.
Drift Pin Alignment
Upper Section
3/8”x 1 1/4” Bolt
Flatwasher
Flat Butyl
Sealer Tape
Flatwasher
Lockwasher
Nut
Lower Section
9. Insert a drift pin per
Figure 5
. Start at the corner hole and skip every 3 or 4 holes
along the length of the unit. Repeat this process on the other side.
10. Lower the upper section the remaining distance using the alignment pins and drift
pins to align the coil casing section and lower section holes.
11. Fasten the hardware between the coil casing and lower section per
Figure 6
.
12. Position the hose connecting the sections of the pump discharge pipe and secure with
the hose clamps provided.
Section Assembly of Optional Three-Piece Cells
1.
Figures 7a, 7b, and 7c
show the proper rigging of sections for units that ship in three
sections.
2. Remove any motors or accessories shipped in the lower section.
Figure 7a.
Lower Section Three-Piece Lift
Figure 7b.
Coil Casing Section Three-Piece Lift
Figure 7c.
Mechanical Section Three-Piece Lift
H
W
H
W
H