Hardware Location for unit with internal platform
Unit Weights
Before rigging any BAC equipment, the weight of each section should be verified on the unit certified drawing.
These weights are
approximate
and should be confirmed by weighing
before lifting
when available
hoisting capacity provides little margin for safety.
Caution
BEFORE AN ACTUAL LIFT IS UNDERTAKEN, ENSURE NO WATER, SNOW, ICE OR DEBRIS
HAS COLLECTED IN THE SUMP OR ELSEWHERE IN THE UNIT. SUCH ACCUMULATIONS WILL
ADD SUBSTANTIALLY TO THE EQUIPMENT’S LIFTING WEIGHT.
In the event of extended lifts or where hazards exist, the lifting devices should be used in conjunction with safety
slings placed under the unit.
Anchoring
The unit must be properly anchored in place.
Refer to the suggested support details on the certified drawing for locations of the mounting holes. Anchor bolts
must be provided by others.
Holes suitable for 20 mm bolts are provided in the bottom flange of the lower section for bolting the unit to the
support beams.
Leveling
The unit must be level for proper operation and ease of piping.
Support beams must also be level as shims should not be used between pan and support beams to level the unit.
Connecting Pipework
All piping external to BAC cooling equipment must be supported separately.
W W W . B A L T I M O R E A I R C O I L . E U
7
1 General Information
1 General Information
Summary of Contents for S1500E
Page 22: ...W W W B A L T I M O R E A I R C O I L E U 22...
Page 23: ...W W W B A L T I M O R E A I R C O I L E U...
Page 24: ...W W W B A L T I M O R E A I R C O I L E U...
Page 25: ...W W W B A L T I M O R E A I R C O I L E U...
Page 26: ...W W W B A L T I M O R E A I R C O I L E U...