25
1
2" (5,1 cm)
PARTS REQUIRED:
x8
FRONT WALL INSTALLATION
x6
Center front wall assembly on fl oor, resting top plate on side walls.
Secure front wall top plate to side walls using (2) 3" screws
(Fig. A, B)
.
Secure lower edge of panel to fl oor frame using (8) 2" nails 6" apart.
Angle nail to hit fl oor frame
(Fig. C)
.
2
Secure bottom plates using (3) 3" nails on each side
(Fig. C)
.
3
You have fi nished standing your walls.
FINISH
Nail front wall to side walls using 1-1/2" nails 6" apart
(Fig. D)
.
4
5
3" (7,6 cm)
x26
1-1/2" (3,8 cm)
It is important to secure the
front wall in the following order:
BEGIN
Flush
Flush
Center wall assembly on
Maintain 56” dimension
oor.
(2) 3" (7,6 cm)
Screws
Fig. A
Fig. B
Nail 2" nails rst.
Angle to nail into
oor frame.
Fig. C
2" (5,1 cm) Nails
3" (7,6 cm) Nails
3" (7,6 cm) Nails
1-1/2" (3,8 cm)
Nails
Fig. D
3" (7,6 cm)
x4