Installation
Seite 8
December 2019
AC_F001_IA_02_2243
4.1.3. INSTALL THE BODY
1. As applicable, remove the knock-out ports (2) and install the cable glands
(3).
2. As applicable, mark and drill the mounting holes in the structure (4).
3. Hold the body (1) in the correct position for installation.
4. Attach the body (1) with the screws (5) to the structure (4).
Figure 4: Install the body
4.2. Electrical installation - General
WARNING
ONLY QUALIFIED AND WELL-TRAINED PERSONS WHO ARE FAMILIAR WITH THE ELECTRICAL INSTALLATION AND THE
SERVICE PROCEDURES AND WHO OBEY THE SPECIFIC REGULATIONS AND REQUIREMENTS SET BY THE AUTHORITIES,
THE MANUFACTURER, THE EMPLOYER AND THE PLANT OWNER, ARE ALLOWED TO DO THE ELECTRICAL WORK.
4.2.1. PREPARATION
1. Ask the responsible (safety) staff for permission to lock-out / tag-out a part of the installation or system and to do any
required work.
2. Lock-out and Tag-out the F001 and the related system.
3. Make sure, the work area is safe.