Basic Installation and Setup steps
1. Determine where the Reader will be installed
2. Run wiring to the mounting point for power & communications
3. Pour concrete pad for post mount
4. Secure mounting post and BA-220 DualBeam to the pad
5. Connect power & communications to the reader
6. Place decals on vehicles
(the same side the reader will be on)
7. Turn Power Switch On
8. You're up & running
If the BA-220 DualBeam was not set up for your specific installation at
the Factory you will have to configure the Reader after it is mounted in
place. To do this refer to the Operation and Configuration Manual for
details
.
Determine where the BA-220 DualBeam will be installed:
Overhead view of Installation
As shown in this figure, the reader should be located at least one car
length (plus a small gap) before the gate. It does not matter which
side of the road it is mounted on, as long as the vehicle decals are on
the same side.
Always locate the reader and decals on the same
side of the car.
18’ to 25’
Approx 1
car length
BA-220 DualBeam