MAINTENANCE
EQUIPMENT AND TOOLS REQUIRED
6 - 2
I-E96-117B
®
The following items should not be serviced on the IISAC01
Analog Control Station. Do not attempt to:
1. Calibrate the SAC station.
2. Adjust the SAC station bar graph intensity.
3. Replace discrete components on the SAC station.
EQUIPMENT AND TOOLS REQUIRED
The following are the tools and equipment required for mainte-
nance procedures.
•
Antistatic vacuum.
•
Clean, lint-free cloth.
•
Compressed air.
•
Eberhard Faber (400A) pink pearl eraser.
•
Fiberglass or nylon burnishing brush.
•
Foam tipped swab.
•
Bladed screwdriver.
•
Isopropyl alcohol (99.5% electronic grade).
•
Natural bristle brush.
PREVENTIVE MAINTENANCE PROCEDURES
This section covers tasks from Table
(preventive mainte-
nance schedule) that require specific instruction or further
explanation. The tasks and instructions covered are:
•
Printed circuit board cleaning.
•
How to check signal, power and ground connections.
Table 6-1. Preventive Maintenance Schedule
Task
Frequency
Check SAC faceplate, circuit board and housing for dust.
Clean as necessary using an antistatic vacuum.
3 months
Check all signal, power and ground connections associated
with the SAC station and its termination device; verify that
they are secure. See procedure.
Check circuit boards, giving particular attention to power con-
tacts. Clean as necessary. See procedure.
12 months
Complete all tasks in this table.
Shutdown