Recommended rigging method for 6 m long units
Recommended rigging method for 6 m long units
1. Safety slings (for extended lifts)
2. Lifting ear
3. Lifting cable
Recommended arrangement for rollers used for final positioning
1. 4 Rollers required (2 each side)
2. Floor
TANK SIZE
Width "W" (mm)
High units
Low units
TSU-476M
TSU-L370M
2400
TSU-594M
TSU-L462M
2980
TSU-761M
TSU-L592M
3600
Dimensions for 6 m long units
System charging
Coils are filled in the factory with nitrogen. Release the nitrogen in a properly ventilated area, before charging the
system with glycol. The system should be filled with an industrial grade inhibited ethylene glycol solution, typically
25% (-10°C freezing point) concentration.
W W W . B A L T I M O R E A I R C O I L . E U
11
2 Rigging