background image

Caution

BEFORE AN ACTUAL LIFT IS UNDERTAKEN, ENSURE NO WATER, SNOW, ICE OR DEBRIS

HAS COLLECTED IN THE UNIT. SUCH ACCUMULATIONS WILL ADD SUBSTANTIALLY TO THE

EQUIPMENT'S LIFTING WEIGHT.

Leveling

The unit must be level for proper operation and ease of piping.
When the unit is installed on a concrete slap, this one should have a levelness or maximum slope of 3mm per

3meter and the flatness should be no more than 4mm over a 2m span.
Support beams must also be level as shims should not be used between pan and support beams to level the unit.

Connecting Pipework

All piping external to BAC cooling equipment must be supported separately.
In case the equipment is installed on vibration rails or springs, the piping must contain compensators to eliminate

vibrations carried through the external pipework.
All connections in the external pipework (installed by others) must be leak free and tested accordingly.
Suction pipe sizing should be done according to good practice, which may for larger flows require larger pipe

diameters than the outlet connection. In such cases adapter pieces need to be installed.

Coil Connections

Coils of BAC Ice thermal Storage Units are filled with a low pressure inert gas at the factory before shipping, to

ensure an optimal internal corrosion protection. It is recommended to check the overpressure every six months

(connect a manometer to the valve).
On site, the pressure needs to be released from the coil. Remove the plug first before opening the pressure relieve

valve.
Next the connections need to be cut at 1cm from the end. Make sure to protect the unit against sparks from the

cutting process with a suitable material.
In case of threaded connections, clean up the thread prior to connecting it to the pipework.
Non-threaded connections must be bevelled on site before they can be welded.

Non-threaded Coil Connection with pressure release valve on Ice Thermal Storage unit for Direct Refrigerant Feed.

W W W . B A L T I M O R E A I R C O I L . E U

5

1 General Information

1 General Information

Summary of Contents for TSU 1050C

Page 1: ...TSU C D ICE CHILLER Thermal Storage Unit for external melt RIGGING AND INSTALLATION INSTRUCTIONS RTSU CDv02EN...

Page 2: ...antity controller condition of sensor conductivity of tank water X X X Air Pump Air Filter Replacement X X X Refrigerant Glycol quality NH3 purge oil X X Air Distribution Piping X Cleaning procedures...

Page 3: ...ting Pipework 5 Coil Connections 5 Freeze Protection 6 Safety Precautions 6 Non walking Surfaces 7 Modifications by others 7 Warranty 8 2 Rigging 9 General Notes 9 Support Requirements 9 Rigging Metho...

Page 4: ...e unit is delivered to the jobsite it should be checked thoroughly to ensure all required items have been received and are free of any shipping damage prior to signing the bill of lading The following...

Page 5: ...n pipe sizing should be done according to good practice which may for larger flows require larger pipe diameters than the outlet connection In such cases adapter pieces need to be installed Coil Conne...

Page 6: ...to prevent damage to the equipment its associated system and the premises If there is doubt about safe and proper rigging installation operation or maintenance procedures contact the equipment manufa...

Page 7: ...D LOAD CAUSING SEVERE INJURY DEATH AND OR PROPERTY DAMAGE LIFTS MUST BE PERFORMED BY QUALIFIED RIGGERS FOLLOWING BAC PUBLISHED RIGGING INSTRUCTIONS AND GENERALLY ACCEPTED LIFTING PRACTICES THE USE OF...

Page 8: ...e event of any such defect BAC will repair or provide a replacement For more details please refer to the Limitation of Warranties applicable to and in effect at the time of the sale purchase of these...

Page 9: ...s may result in serious damage of the tank bottom and the ice coils 4 Spreader bars of the full width of the section must be used between the lifting cables to prevent damage to the section 5 For exte...

Page 10: ...on I beams additional insulation of the tank bottom is necessary to avoid the formation of condensation Installation on 3 I beams ON A ROOF For installation of the unit on a roof additional field insu...

Page 11: ...ME TANK COVERS MUST BE REMOVED TO PROVIDE ACCESS TO THE LIFTING EARS ENSURE THAT THE LIFTING CABLES DO NOT DAMAGE THE REMAINING COVERS Three lifting beams are required The lifting ears and tank are no...

Page 12: ...22 x 2982 12725 x 2982 9090 10515 11850 13820 15205 17455 3430 4618 5889 5941 6300 6899 1333 1336 1310 1881 2311 2913 2797 2797 2797 2797 2797 2797 TSU 790D TSU 940D TSU 1080D TSU 1220D TSU 1440D 7290...

Page 13: ...led The recommended air piping is shown in the figure the air supply is taken from the ambient air The air pump is to be mounted on a clean dry and vibration free surface which is flat and will suppor...

Page 14: ...rating and Maintenance Manual see Table Recommended Maintenance and Monitoring Programme on page 2 must be performed Proper start up procedures and scheduled periodic maintenance will prolong the life...

Page 15: ...specific assistance at www BaltimoreAircoil eu More Information REFERENCE LITERATURE Eurovent 9 5 6 Recommended Code of Practice to keep your Cooling System efficient and safe Eurovent Cecomaf 2002 3...

Page 16: ...W W W B A L T I M O R E A I R C O I L E U 16...

Page 17: ...W W W B A L T I M O R E A I R C O I L E U...

Page 18: ...W W W B A L T I M O R E A I R C O I L E U...

Page 19: ...W W W B A L T I M O R E A I R C O I L E U...

Page 20: ...VE CONDENSERS HYBRID PRODUCTS PARTS SERVICES www BaltimoreAircoil eu info BaltimoreAircoil eu www balticare com info balticare com Please refer to our website for local contact details Industriepark Z...

Reviews: