36 / 61
0006080103 ed2005/10
LDU 11.. GAS VALVE TIGHTNESS CONTROL EQUIPMENT
Use
LDU 11 equipment is used to verify tightness of valves on natural gas burners.
The LDU 11 combined with a normal pressure switch automatically verifi es tightness of natural gas burners
valves, before every start up and immediately after each stop.
Tightness control is carried out by two-stage verifi cation of gas circuit pressure in the section between the two
burner valves.
Operation
During the fi rst stage of the tightness control (TEST 1), the pipeline between the valves being checked must be at
atmospheric pressure. In plant without atmospheric pressure setting pipes, this pressure is achieved by tightness
control equipment. The latter opens the valve on the furnace side for 5 seconds during “
t4
” time.
When the 5 seconds are up, the furnace side valve is closed.
During the fi rst phase (
TEST 1
) the control equipment ensures that atmospheric pressure in the pipes is kept
constant.
Surveillance is carried out by the “
DW
” thermostat.
If there is blow-by in the safety valve while closing, pressure increases and as a result the “
DW
” pressure switch
operates. For this reason, in addition to indicating pressure, the equipment goes into fault state and the position
indicator stops blocked in the “
TEST 1
” position (red pilot lamp lit).
Vice-versa, if pressure does not increase because there is no blow-by in the relief valve as it closes, the equip-
ment immediately programmes the second stage “
TEST 2
”.
Under these conditions, the relief valve opens for 5 seconds during “
t3
” time and introduces gas pressure into
the pipeline (“fi lling operation”). During the second verifi cation stage, this pressure must remain constant.
Should it drop, this means that the burner on the furnace side has a blow-by (fault) when closing.Therefore the
“
DW
” pressure switch operates and the tightness control equipment prevents burner start-up and stops in bloc-
ked state (red pilot lamp lit). If second stage verifi cation is positive, the LDU 11 equipment closes the internal
control circuit between terminals
3
and
6
(terminal
3
- contact
ar2
- outer cross-connection for terminals
4
and
5
- contact
III
- terminal
6
).
This is the circuit that usually enables the equipment start-up control circuit. After circuit between terminals
3
and
6
has closed, the LDU 11’s programmer returns to rest position and stops. This means it enables fresh verifi cation
without changing the position of the programmer’s control contacts.
N.B.
Adjust the “
DW
” pressure switch to about half the pressure of the gas supply network.
Key to symbols :
}
Start-up = operating position
In plants without a bleed valve = test circuit put under atmospheric pressure by opening
of valve on the furnace side of the burner.
TEST 1
“TEST 1” pipeline at atmospheric pressure (blow-by verifi cation at closure of relief valve)
Putting test circuit gas under pressure by opening of relief valve
TEST 2
“TEST 2” pipeline at gas pressure (blow-by verifi cation of valve on furnace side of burner)
III
Automatic zero (or inoperative mode) reset of programmer
}
Operation = set for new blow-by verifi cation
If trouble is signalled, there is no voltage in all control equipment terminals excepting terminals
13
which gives
remote, visual indication of trouble.
When verifi cation is over, the programmer automatically returns to rest position, and is ready to carry out a further
programme for checking tightness of valves as they close.
Summary of Contents for GI MIST 350 DSPGM
Page 40: ......
Page 41: ......
Page 42: ......
Page 43: ......
Page 44: ......
Page 45: ......
Page 46: ......
Page 47: ......
Page 48: ......
Page 49: ......
Page 50: ......
Page 51: ......
Page 52: ......
Page 53: ......
Page 54: ......
Page 55: ......
Page 56: ......
Page 57: ......
Page 58: ......
Page 59: ......