SUPPLY LINE
The figure below shows the gas supply line block diagram.
Install a manual shut-off valve and an anti-vibration joint upstream
of the gas valve, as shown in the diagram.
If the gas train is equipped with a pressure regulation device not
integrated in a monoblock valve, follow the instructions below to
install the accessories on the gas pipe near the burner:
•
To avoid high pressure drops upon ignition, there should be
a 1.5/2 m long pipe section between the pressure reducer or
stabiliser installation point and the burner. The tube diameter
should be equal to or greater than the burner attachment union.
To ensure optimal operation of the pressure regulator, it should be
applied to the horizontal pipe after the filter.
The gas pressure regulator must be adjusted when it is working at
the maximum output actually used by the burner.
The delivery pressure must be adjusted to a level slightly below
the maximum obtainable.
BURNER CONNECTION TO THE BOILER
HEAD UNIT ASSEMBLY
•
Position the insulating gasket (13) on the sleeve, by inserting
the cord (2) between the flange and the gasket.
•
Adjust the position of the coupling flange (19) by loosening the
screws (6) so that the burner head enters the furnace to the
extent recommended by the generator manufacturer.
•
Fasten the burner to the boiler (1) by means of the stud bolts,
washers and the nuts provided (7).
DANGER / ATTENTION
Seal the space between the burner sleeve and the hold on
the refractory material inside the boiler door completely with
suitable material.
0002935610
19
2
1
7
6
13
Summary of Contents for TBG 35P
Page 2: ......
Page 34: ...ITALIANO 32 34 0006160258_201802 ...
Page 36: ...ITALIANO 34 34 0006160258_201802 ...
Page 68: ...ENGLISH 32 34 0006160258_201802 ...
Page 70: ...ENGLISH 34 34 0006160258_201802 ...
Page 71: ......