TYPICAL INSTALLATION
1
Motor
2
Photocells
3
Key selector
4
Blinker
5
Receiver / Antenna
CHECKING BEFORE INSTALLATION
Before doing the installation is suggested to do the following
operations:
The structure of the gate must be sturdy and appropriate;
During the run, the gate don’t have to present too much sideways
slide skids.
The system of wheels/lower rail and roller upper runner must work
without too many frictions;
To avoid the gate derailment, is necessary to install the stop beats
of the sliding, whether at the opening or the closing, and a second
roller/runner in full observance of the current law.
Remove the manual lock in the before hands gates;
Put on the bottom of the gate the feed raceway of the feeding
cables (025-50mm) and of external connection (photocell, blinker,
key selector, etc.)
PROGET is responsible only of the products that produce and
commercialize. The gate when automate, becomes a machinery and
so is subjected to the Machinery Normative. Therefore is duty of the
installer to verify the safety of the whole installation.
WARNING: PROGET in not responsible for damages to persons,
animals or objects caused by modifications done without permission,
to his products.
IMPORTANT WARNINGS
This equipment is exclusively intended for the usage it was
conceived, any other kind of usage is to be considered improper
and therefore dangerous.
The installation and the maintenance (every 6 months) of the
product have to be carry out only by specialized staff according to
the current laws.
The feeding voltage has to be supplied from an efficient
differential pushbutton, which has to be tested and settled
according to the current laws and also a suitable external
independent disconnecting switch, which has to be adjusted on
the current charge.
Throughout the installation procedure the board has to be switch
off.
The disposition of materials has to be done in accordance with the
current laws.
Adopt all the precautions to integrate the safety of the gate in
accordance with the current laws.
Choose the shortest ways for the cables and keep power cables
away from the control ones.
Before the installation assure that there is the stopping beat of the
gate.
For the adjustment of the maximum torque of the gear motor,
follow the current laws.
According to the European laws on security, we suggest to
connect an external pushbutton for switching off the feeding
during maintenance on the gate.
Verify that all the installed devices are effective and efficient.
Post-up sign-boards in a readable way to inform the presence of
an automatic gate
Please remember that we are in the presence of an automatic device
fed with electric energy, therefore use it with all the precautions. In
particular we exhort:
Don’t touch the device with wet hands and/or with wet or naked
feet;
Cut the energy before opening the command box and/or the
motor;
Don’t pull the feeding cable to disconnect the plug;
Command the motorized gate only when it is completely visible;
Stay out of the action range of the gate, if this is in motion: wait
until it’s completely stopped;
Don’t let the children or the animals play in the proximity of the
gate;
Don’t let the children use the radio-control or other command
devices of the gate;
Do a periodical maintenance;
In case of damage, cut the energy and move the gate manually
only if it is possible and safe.
Avoid any self-made intervention but call specialized stuff.