Important!
Possible damage to device!
•
Commissioning and maintenance work is only permitted to be performed when the power is
switched off. The power cable must also be disconnected from the power supply and device.
•
Do not use force! Handle all the modules and components carefully.
•
All covers, components, accessories, hardware and cables must be installed or connected be-
fore the device can be connected to the power supply and switched on.
•
Observe the ESD notes (see
"Protection against electrostatic discharge" on page 6
).
Important installation information
•
The environmental conditions must be observed.
•
When installed in a closed housing, enough space must be available for air to circulate sufficiently.
•
The device must be installed on a flat, clean and burr-free surface.
•
Ventilation holes are not permitted to be covered.
•
You must observe the permissible mounting orientations when installing the device.
•
When connecting cables, the bend radius must be taken into account.
•
The device must be installed such that viewing is optimized for the user.
Only 2 screws are needed in order to adhere to the mechanical properties. For this reason, the cover of the Power
Panel is installed using 2 screws when delivered.
Some devices have unused drill holes that can be used for additional installation purposes (e.g. top-hat rail instal-
lation).