5.1 Installation process overview
Installation process from A to Z
1.
Check if all installation requirements are fulfilled
such as the environment conditions of the installation
area, electrical facilities, etc. Note that a solid pedestal is required to support the projector. For more info see
topic
, page 36.
Tip:
Barco offers a pedestal for the Thor series series projector. This pedestal allows for a solid and
easy setup of the projector and chillers that fit underneath the pedestal.
2.
Physical installation of the chiller.
One chiller has to be installed. Follow precisely the installation
instructions delivered with the chiller. Only by Barco approved chillers may be used. Ensure that the distance
between the chiller and projector can be bridged with the hoses delivered with the system. Take into account
that the height difference between chiller coupling and projector coupling should be less than 3 meter.
Note:
The chiller must be equipped with the cooling circuit expansion unit for the projector DMD
cooling. See chapter chapter
”
, page 28. This expansion unit has be installed on
site. See installation instructions delivered with the chiller.
Note:
Ensure to install the correct address plug for the chiller. The chiller which is equipped with the
cooling circuit expansion unit has a different address plug installed. See installation instructions
delivered with the chiller.
3.
Physical installation of the projector
upon its pedestal. Position the projector correctly on its pedestal and
then remove the transport protection bars at the front and at the rear side of the projector. See chapter
”
, page 45.
4.
Capture condensed water
. Guide the small drain tubes at the bottom of the projector directly to a water
drain. If no water drain is available then an 'open' water container must be installed to capture the condensed
water coming out of the small drain tubes. See chapter
, page 36.
5.
Installing the hoses and communication cables between chiller and projector.
Note that only by Barco
approved hoses may be used. See chapter
Connecting the hoses with projector and chillers
”
, page 49, and
chapter
“
Connecting the data cable with projector and chillers
”
, page 51.
6.
Installing the isolation shells
at both ends of the hoses. An accessory kit containing the isolation shells is
delivered separately. For precise installation instructions see documentation included in the accessory kit.
7.
Installing the external safety interlocks
if needed. It's up to the Laser Safety Officer to investigate the need
of external safety interlocks and to ensure a correct installation of the external safety interlocks when needed.
For more info about external safety interlocks see chapter
“
”
, page 30. For installation
instructions see chapter
“
Connecting the external safety interlocks
”
, page 53.
8.
Power input set up and electrical connection with the mains electricity
. First check if the three phase
configuration (Y-Δ) of the projector matches with the voltage of the mains electricity. To adapt the configuration
see chapter
Three phase power input configuration of the projector
”
, page 54. Then connect the projector
with the mains electricity. See chapter
Connecting the projector with the mains electricity
, page 55.
9.
Installation of a suitable UPS unit or bypass
the power in and outlet for the projector electronics. See
chapters
Connecting a UPS to the projector electronics
, page 57 or
Power loop through to the projector
”
, page 56.
10.
Installation of the Communicator Touch Panel
. See chapter
“
Installing the Communicator Touch Panel
,
11.
Installation of the lens
. First select a lens with appropriate throw ratio covering the screen size and the
projector - screen distance. Then install the lens in the lens holder of the projector. For more information about
available lenses, lens selection and lens installation see chapter
, page 61.
Caution:
The projector is delivered with a protective cover inside the Lens Holder. Remove the cover
prior to installing the lens.
12.
Installation of the ICMP or IMB
. (only in case no ICMP or IMB is factory installed).
13.
Installation of the HDDs.
In case the HDDs of the ICMP are delivered separated from the projector remove
the protection tape from the HDD input slots and install all three HDDs as described in the procedure
Summary of Contents for Thor Series
Page 1: ...ENABLING BRIGHT OUTCOMES Installation manual Thor series...
Page 2: ...Barco NV President Kennedypark 35 8500 Kortrijk Belgium www barco com en support www barco com...
Page 8: ...R5906788 03 Thor series 8...
Page 24: ...R5906788 03 Thor series 24 Safety Information...
Page 26: ...R5906788 03 Thor series 26 Commander Web Commander System overview...
Page 44: ...R5906788 03 Thor series 44 Installation process...
Page 68: ...R5906788 03 Thor series 68 Lenses Lens selection...
Page 78: ...R5906788 03 Thor series 78 Installing a HDD into the ICMP ICMP...
Page 110: ...R5906788 03 Thor series 110 Starting up...
Page 122: ...R5906788 03 Thor series 122 Scheimpflug...
Page 130: ...R5906788 03 Thor series 130 Convergence...
Page 142: ...R5906788 03 Thor series 142 Preventative maintenance actions...
Page 160: ...R5906788 03 Thor series 160 Specifications...
Page 168: ...R5906788 03 Thor series 168 Pin configurations...
Page 172: ...R5906788 03 Thor series 172 Environmental information...
Page 176: ...Glossary R5906788 03 Thor series 176...
Page 181: ...R5906788 03 Thor series 181...
Page 182: ...Barco NV President Kennedypark 35 8500 Kortrijk Belgium www barco com R5906788 03 07 09 2018...