6.1 Switching the Thor ON
About the start up process
To start up the Thor the sealed compartment of the Light Processor and the sealed compartment of the Laser
Clusters must be brought into a 'condition' which is safe for the electronics to operate (avoid moisture due to
extreme cooling). In other words, the temperature and humidity inside these compartments must be brought
within specs prior to activating the lasers and Light Processor. The time needed to bring the projector from a
deconditioned
state into a
conditioned
state depends on the ambient conditions and can take several
minutes. This process is called
conditioning
.
Start up checklist
1.
Check if the chiller is correctly installed. See documentation set of the chiller.
2.
Check if the chiller is equipped with the expansion unit for DMD cooling.
3.
Check if the Thor is installed onto a stable platform and all covers are installed..
4.
Check if all hoses are properly connected with the chiller and projector. .
5.
Check if the data cables between chiller and projector are correctly installed.
6.
Check if the projector is connected with the mains electricity.
7.
Check if the ambient temperature and humidity are within specifications..
8.
Check if the chiller, hoses and projector are completely acclimatized to the same ambient temperature.
9.
Check if the correct lens is installed for the application and the lens cap is removed from the lens. See
chapter
, page 23.
10.
Check if the small drain tubes at the bottom of the projector leads to a water drain or to an open reservoir to
capture the condensed water.
Keep in mind that it can take up to 10 minutes to start the lasers again after they were switched off.
If there are only 30 to 45 minutes between the shows it
’
s advisable to keep the lasers on with
dowser closed. When the dowser is closed the lasers are automatically dimmed.
Start up procedure
1.
Switch on the chiller. The status light of the chiller should light up white. See documentation set of the chiller.
2.
Press the
Power Switch
to switch the projector
ON
.
As a result the Controller of the projector starts up. All other electronics remain off. The booting process is
indicated by the
blue blinking backlight
of the Standby button on the local keypad. Once the Controller is up
and running the backlight of the Standby button is changed to continuous white. This is the projector Standby
mode. The status light of the projector also flashes green.
Note:
The projector always boots up in the same mode (E.g. Standby or Operation) as it was switched
off. This procedure assumes that the projector was switched off in Standby mode.
3.
Press the
STANDBY
button on the Local Keypad for three seconds or use the Communicator to put the
projector in
OPERATIONAL
mode.
As a result the backlight of the Standby button starts blinking green indicating the start up of all other projector
electronics. Once this initializing process is done the backlight of the Standby button is changed to continuous
green. This is the projector Operational mode. The status light of the projector also lights up green (not
flashing).
4.
Press the
LIGHT
button on the Local Keypad for three seconds or use the Communicator to activate the
lasers.
As a result the backlight of the Light button starts blinking green indicating the projector is in CONDITIONING
mode. The laser status light on the top of the projector flashes a few times and then lights up continuously
white.
Once the projector is conditioned the backlight of the Standby button is changed to continuous green. Now the
lasers are active and light can come out of the projector. The status light of the projector remains green and
the status light of the lasers remains white.
Summary of Contents for Thor Series
Page 1: ...ENABLING BRIGHT OUTCOMES User manual Thor series...
Page 2: ...Barco NV President Kennedypark 35 8500 Kortrijk Belgium www barco com en support www barco com...
Page 28: ...R5906787 04 Thor series 28 Lenses Lens selection...
Page 74: ...R5906787 04 Thor series 74 Starting up...
Page 90: ...R5906787 04 Thor series 90 Environmental information...
Page 94: ...Glossary R5906787 04 Thor series 94...
Page 98: ...Barco NV President Kennedypark 35 8500 Kortrijk Belgium www barco com R5906787 04 2019 10 23...