Introduction to Testing
54 • Introduction to Testing
The need to test protection systems to confirm performance as designed by manufacturers has always
existed. However, numeric system design is changing the industry testing paradigms that have been in
use since the first protective relay was built. Each time a fault occurs, the numeric protection system is
tested, and because of its fault and event recording capability, the test is documented. In the unlikely
event of a protection system problem, continuous monitoring along with remote communications
capability provide for removing the affected device from service, auto switching to backup systems, and
immediate notification of an attended facility. These features have virtually eliminated the need for
periodic maintenance. Simple acceptance tests that verify the integrity of the BE1-11
m
measuring circuits
and commissioning tests that verify the BE1-11
m
“electronic wiring” (control logic) are Basler Electric’s
recommended pre-installation tests.
The testing chapters provide guidelines for performing these tests and others. For assistance in
conducting BE1-11
m
self-tests and troubleshooting using internal diagnostics, contact Basler Electric
Technical Support Services.
Testing Philosophies
Testing is generally divided into the following categories:
•
Acceptance
•
Commissioning
•
Periodic (user scheduled maintenance)
•
Functional
While all types of tests can be performed, all users do not generally perform these tests. Likewise, the
degree to which you will conduct each type of test depends on need, economics, and perceived system
value.
Acceptance Testing
Acceptance testing confirms that a particular BE1-11
m
delivered to a customer meets published
specifications. Because this is a numerical BE1-11
m
whose characteristics are defined by software,
Basler Electric does not require the user to test each operational setting in the BE1-11
m
. Successful
completion of the Acceptance Test verifies proper response of the protection system’s input and output
circuits as well as its response to all external sensing input quantities (voltage, current, frequency).
Basler Electric performs detailed acceptance testing on all devices to verify all functions meet published
specifications. All products are packaged and shipped with the strictest standards. The BE1-11
m
is a
microprocessor-based device whose operating characteristics will not change over time. The BE1-11
m
will also not experience any change in operating characteristics during transit. However, it remains
important that the user perform these acceptance tests to verify the device has not suffered any
degradation in transit. Basler Electric warrants all products against any decay in performance outside of
the published specified tolerances that result from problems created during transit.
Commissioning Testing
Commissioning testing verifies all physical connections and functional aspects of the BE1-11
m
for a new
installation. This includes a thorough review and documentation of the operational settings to verify that
the users calculated values match the actual values on each enabled protection element of the BE1-11
m
.
All of the following connections or functions can be verified during commissioning tests:
•
Proper connection and sensing of current and voltage signals as applicable
•
Connections of I/O contacts
•
I/O sensing versus virtual sensing
Summary of Contents for BE1-11m
Page 8: ...vi 9424200996 Revision History BE1 11m...
Page 12: ...x 9424200996 Contents BE1 11m...
Page 21: ...9424200996 1 9 BE1 11m Introduction Figure 1 1 Style Chart...
Page 22: ...1 10 9424200996 Introduction BE1 11m...
Page 40: ...3 6 9424200996 Controls and Indicators BE1 11m Figure 3 3 Front Panel Display Setup Screen...
Page 54: ...5 6 9424200996 Phase Undervoltage 27P Protection BE1 11m...
Page 56: ...6 2 9424200996 Negative Sequence Voltage 47 Protection BE1 11m...
Page 61: ...9424200996 7 5 BE1 11m Phase Overvoltage 59P Protection Figure 7 3 Overvoltage Settings Screen...
Page 62: ...7 6 9424200996 Phase Overvoltage 59P Protection BE1 11m...
Page 68: ...8 6 9424200996 Auxiliary Overvoltage 59X Protection BE1 11m...
Page 80: ...12 4 9424200996 Instantaneous Overcurrent 50 Protection BE1 11m...
Page 84: ...13 4 9424200996 Breaker Failure 50BF Protection BE1 11m...
Page 92: ...14 8 9424200996 Inverse Overcurrent 51 Protection BE1 11m...
Page 105: ...9424200996 18 3 BE1 11m Power Factor 55 Protection Figure 18 2 Power Factor Settings Screen...
Page 106: ...18 4 9424200996 Power Factor 55 Protection BE1 11m...
Page 110: ...19 4 9424200996 Resistance Temperature Detector 49RTD Protection BE1 11m...
Page 118: ...20 8 9424200996 Thermal Curve 49TC Protection BE1 11m...
Page 122: ...22 2 9424200996 Starts per Time Interval 66 Protection BE1 11m...
Page 124: ...23 2 9424200996 Restart Inhibit Protection BE1 11m...
Page 140: ...28 4 9424200996 Breaker Control Switch 101 BE1 11m...
Page 148: ...29 8 9424200996 Setting Groups BE1 11m...
Page 156: ...30 8 9424200996 Metering BE1 11m Figure 30 11 RTD Meter Screen...
Page 158: ...31 2 9424200996 Digital Points BE1 11m Figure 31 2 Digital Points Monitor Screen...
Page 177: ...9424200996 34 5 BE1 11m Motor Reporting Figure 34 9 Learned Motor Data Screen...
Page 178: ...34 6 9424200996 Motor Reporting BE1 11m...
Page 184: ...35 6 9424200996 Alarms BE1 11m...
Page 186: ...36 2 9424200996 Differential Reporting BE1 11m...
Page 196: ...38 4 9424200996 Demands BE1 11m...
Page 198: ...39 2 9424200996 Load Profile BE1 11m...
Page 208: ...41 6 9424200996 Trip Circuit Monitor 52TCM BE1 11m...
Page 212: ...42 4 9424200996 Fuse Loss 60FL BE1 11m...
Page 218: ...43 6 9424200996 BESTnet Plus BE1 11m Figure 43 8 Power Quality Page...
Page 221: ...9424200996 44 3 BE1 11m Mounting Figure 44 3 Case Side Dimensions...
Page 235: ...9424200996 45 5 BE1 11m Terminals and Connectors Figure 45 7 Example of Reversed CT Polarity...
Page 236: ...45 6 9424200996 Terminals and Connectors BE1 11m...
Page 269: ...9424200996 48 15 BE1 11m BESTlogic Plus Figure 48 4 Logic Page 1 for Default Logic...
Page 288: ...49 10 9424200996 Communication BE1 11m Figure 49 14 Modbus Mapping Screen...
Page 306: ...52 4 9424200996 Device Information BE1 11m...
Page 314: ...53 8 9424200996 Configuration BE1 11m Figure 53 3 Display Units Screen...
Page 318: ...54 4 9424200996 Introduction to Testing BE1 11m...
Page 330: ...56 6 9424200996 Commissioning Testing BE1 11m...
Page 336: ...58 4 9424200996 Phase Undervoltage 27P Test BE1 11m...
Page 340: ...59 4 9424200996 Phase Overvoltage 59P Test BE1 11m...
Page 352: ...60 12 9424200996 Auxiliary Overvoltage 59X Test BE1 11m...
Page 360: ...61 8 9424200996 Frequency 81 Test BE1 11m...
Page 364: ...62 4 9424200996 Instantaneous Undercurrent 37 Test BE1 11m...
Page 376: ...63 12 9424200996 Instantaneous Overcurrent 50 Test BE1 11m...
Page 396: ...65 16 9424200996 Inverse Overcurrent 51 Test BE1 11m...
Page 408: ...67 6 9424200996 Power 32 Test BE1 11m...
Page 412: ...68 4 9424200996 Loss of Excitation Reverse Var Based 40Q Test BE1 11m...
Page 426: ...70 10 9424200996 Thermal Curve 49TC Test BE1 11m...
Page 432: ...72 4 9424200996 Starts per Time Interval 66 Test BE1 11m...
Page 436: ...73 4 9424200996 Restart Inhibit Test BE1 11m...
Page 440: ...74 4 9424200996 Virtual Control Switches 43 Test BE1 11m...
Page 450: ...75 10 9424200996 Logic Timers 62 Test BE1 11m...
Page 464: ...79 8 9424200996 Troubleshooting BE1 11m...
Page 480: ...80 16 9424200996 Specifications BE1 11m...
Page 600: ...84 56 9424200996 Settings Calculation Examples BE1 11m Figure 84 70 Logic Page 4 Part 1...
Page 602: ...84 58 9424200996 Settings Calculation Examples BE1 11m...
Page 608: ...85 6 9424200996 BESTCOMSPlus Settings Loader Tool BE1 11m...
Page 609: ......