Vaporsprint
14
2016
Unscrew the valve plug and open the discharge tap (fig. 1), wait for all the water to
come out and then close the tap again. The tap might get clogged: in this case use a
wire with a diameter of 3-4 mm to unclog it.
9.
GOOD FUNCTIONING
VAPORSPRINT was designed for the ironing of domestic garments.
It can be used maximum 20 hrs. per week (subdivided in many times) or 80 hrs. per
month.
10.
INTERVENTIONS AND SMALL REPAIRS
1.
Replace the cover (Prontotop) every 400 hrs. or maximum 6 months. Replace it
also if the vacuum of the board is unsatisfactory or if stains appear on it. This
operation must be carried out with the machine switched off and cold. Stains may
appear if too much steam is used and/or if vacuum function is not used enough (in
this case reduce steam flow and use more vacuum).
N.B.:
the Prontotop can be
washed 1-2 times.
2.
Empty the boiler every 2 or 3 times you use the machine.
3.
Replace the gasket of the safety valve plug (use only original gaskets) every 1200
hrs. of lighting or maximum 2 years, or earlier if it is damaged. Carry out this
operation when the machine is switched off and cold.
4.
If the electric wire is damaged, replace it immediately. The wire is supplied by the
manufacturer or authorized service centres.
11.
COMPULSORY PERIODICAL MAINTENANCE
(To be carried out exclusively by assistance centres or by the manufacturer)
It is recommended to replace:
1.
the internal safety valve every 2100 hrs. of ironing or maximum every 3 years;
2.
the internal thermostat every 2100 hrs. of ironing or maximum every 3 years;
3.
steam tube and iron cable once they seem damaged (fig. 4);
4.
the safety valve plug every 2500 hrs. of ironing or maximum every 3 years (fig.
3).
It is recommended also to clean the boiler from limestone every 2500 hrs. of ironing
or maximum 3 years.
12.
CLOSING OF THE IRONING BOARD
Before closing the table, disconnect plug and make sure the board and the iron are
both cold.
After that, proceed as follows:
1.
unscrew hand-wheel “2” till the leg support is free to rotate (fig. 1, fig. 6);
2.
rotate the leg support and, at the same time, take the board by point
A
till it
closes (fig. 1 and fig. 6);
3.
fix the leg support to its special hook. Keep point
C
pressed and screw hand-wheel
“1” with the other hand (fig. 6).