AGS Simplex 1 ph
1
Suction inlet
2
Exhaust connection
3
Flow regulating valve
4
Drain valve assembly
3.
Check earth continuity:
Ensure that the copper stub pipes which have been brazed to the pipeline system are earthed using suitable
pipe earthing fixtures and sufficient sized cable.
4.
Check operation:
Check operation of exhauster unit in accordance with the commissioning procedure.
5.
Remote start switches:
Position remote switches in appropriate places and wire them in accordance with the relevant wiring
diagram.
%HDFRQ0HGDHV
recommends that Belden 8446 cable is used to wire remote start switches. The black
core should be used for terminal 1, and the white for terminal 3.
6. Glue the biohazard warning label
to the drain flask.
Instruction book
26
Summary of Contents for AGS 1560
Page 2: ......
Page 11: ...Simplified schematic of a AGS Simplex installation Instruction book 9...
Page 13: ...AGS Simplex AGS Duplex Instruction book 11...
Page 16: ...Service diagram AGS Simplex 1 ph typical Instruction book 14...
Page 46: ......
Page 47: ......
Page 48: ......