Always observe all relevant safety instructions.
Initial start-up
To start up the air treatment unit for the first time or after a long period of standstill, proceed as follows:
1. Close the air supply towards the outlet dew point sensor and purge control sensor (if supplied).
2. Close the air supply from the compressor towards the unit by closing both inlet valves.
3. Close the outlet valve.
4. Remove the silencers of the dryers to prevent them from getting clogged by dust from the new desiccant.
Wear a dust mask, safety glasses and ear protection. (This is only required at initial start-up or after the
desiccant was replaced).
5. Start the compressors by starting the ES-MED and wait for pressure.
6. Slowly open the inlet valve of the air treatment unit.
7. Check all connections for air leaks and remedy if necessary.
8. Let the unit operate for several hours with the service commissioning function activated.
9. In case the silencers were removed, refit the silencers.
10. Check the dew point downstream the dMED unit. When the atmospheric dew point has reached -40 ˚C to
-45 ˚C (-40 ˚F to -49 ˚F), open the external outlet valve and set the flow according the specification of the
unit (see section
dMED data
).
Make sure that the flow does not exceed the specified flow and check what is the highest temperature the
ambient air will have.
This flow must not be directed into the air net but needs to be blown off via
another way!
The initial dew point of the air leaving the unit will be higher than normal after starting.
Since the air needs to be according to Pharmacopoeia regulations, it is necessary to run the dryer for
minimum 24 hours with the outlet air blown off to make sure that the pipes are not contaminated.
11. When the atmospheric dew point has reached -48 ˚C (-54 ˚F), it is necessary to perform a validation of
the air quality according Pharmacopoeia.
When the quality of the air is confirmed, change over from blow off circuit to the air system by switching
these valves. The records of these tests must be kept by the user at all times.
12. Gradually open the external outlet valve.
13. Open the air supply towards the purge control sensor.
At initial start-up, and specially when the dryer is loaded from the beginning, it can take a
long time before the dew point is reached.
It is therefore recommended to operate the dryer for a number of days with the outlet valve
closed.
•
All valves, couplings and pipes used/installed after the unit must be free from oil and
grease (hydrocarbon contamination below 550 mg/m
2
) and dust (particles size below
50 micrometer).
•
For the location of the external inlet valve and external outlet valve (customer’s
installation), see section
Installation proposal
.
•
Before starting the unit make sure that all pipes are connected and that items in drains
or pipes for protection during transport are removed.
Instruction book
64
2920 7099 70
Summary of Contents for dMED 100
Page 2: ......
Page 40: ...Inputs Instruction book 38 2920 7099 70...
Page 45: ...Instruction book 2920 7099 70 43...
Page 54: ...4 Installation 4 1 Dimension drawings Instruction book 52 2920 7099 70...
Page 55: ...Instruction book 2920 7099 70 53...
Page 56: ...Instruction book 54 2920 7099 70...
Page 57: ...Instruction book 2920 7099 70 55...
Page 58: ...Instruction book 56 2920 7099 70...
Page 59: ...Instruction book 2920 7099 70 57...
Page 60: ...Instruction book 58 2920 7099 70...
Page 61: ...Instruction book 2920 7099 70 59...
Page 62: ...References on drawings Instruction book 60 2920 7099 70...
Page 93: ......
Page 94: ...No 2920 7099 70 2012 01 Printed in Belgium www beaconmedaes com...