MAINTENANCE
1. Allow 24 hours recharge time after installation or power failure before full load testing.
NOTE: DO NOT LEAVE BATTERIES CONNECTED TO INVERTER, WITHOUT AC INPUT SUPPLIED OR WITH
UNIT SHUTDOWN, FOR A LONG DURATION.
2. Batteries may stop charging if unit detects a fault / error code; seek qualified support as soon as possible.
3. Beghelli recommends that the equipment be tested and that written records be maintained according to the local
building code.
PARTS LIST
1. Cover
2. Cabinet
3. Screws
4. Test Switch (AT
option)
5. Diagnostic
6. Inverter
7. AT Board MT Shelf
8. Toggle Switch
9. Relay
10. Terminal Block
11. Transformer
12. Battery
13. Inverter Display
14. Test Switch (none
AT option)
15. Breaker (option)
16. Sub-plate
17. Heat Shield
Beghelli U.S.A., 3250 Corporate Way, Miramar, Florida, Tel: (800) 726-4316 Tel: (954) 442-6600 Fax: (954) 442-6677
926000443
11/28/2017
OUTPUT to Switched
"Normally ON/OFF" Loads
City AC IN
N
L
L1
Ns
G
Test Button
Ns
L1s
L2s
L2
L1
Ns
L1s
Lamps
Wall Switch Connection
Wall Switch
1
2
3
10
8
11
7
12
9
5
4
14
15
13
16
17
6
AC WIRING DIAGRAM
(with optional