1 697 630 500
2013-03-05
|
Beissbarth GmbH
8 | MS 65 OR RAC S80 | Initial commissioning
en
4. Initial commissioning
4.1
Unpacking
1.
Remove the iron tape and the fixing clamps from the
pallet and the packaging cardboard.
i
After unpacking check the integrity of
MS 65 OR RAC S80 and check that no components
are visibly damaged. In case of doubt do not proceed
to start-up and contact a qualified technician and/or
your vendor.
2.
Take out of the transport crate the standard accesso-
ries and the packaging materials.
i
Dispose correctly of packaging material, hand it over
to the designated collection points.
4.2
Assembly
4.2.1
Cover removal
1.
Unscrew the 4 screws of the side cover and remove
the cover itself.
4.2.2
Lifting of the tilting column
1.
Unscrew the fulcrum-pin screw of the column with
the hex key 6 and remove the pin.
652012-02_Mi
2.
Get a 1 Mt lifting sling, DR 50 model (safety factor
6:1); wrap the sling around the tilting column (1),
extend the bead breaking arm and lift the column
with a hoist (2).
652012-03_Mi
1
2
3.
Remove the external elastic ring with appropriate
pliers and take off the pin.
652012-04_Mi
4.2.3
Column fixing
1.
Align the cylinder rod and the tie rod holes.
652012-05_Mi
2.
Insert the air tube in the slot in the machine box.
3.
Fix the column to the cylinder tank by inserting
the pin with a hammer and tighten the fulcrum-pin
screw.
652012-07_Mi