8.2 Commissioning work
Illustration
Description / explanation
X1
X2
X2
X1
1. Connect the voltage supply.
0
The
BEKOMAT
®
carries out the power-on self-test.
2. Slowly pressurise the system (e.g. by slowly opening
the recommended shut-off valve
[X2]
in the
condensate inlet line
[X1]
).
3. Carry out a functional test (see “10.3.2 Functional test”
BEKOMAT
®
33iU / 33iU CO
Original installation and operation manual
40 | 68