Transport and set-up
CLEARPOINT® L 205 – L295 V
25
12.3 Set-up
Provide suitable lifting tools for the transport and set-up.
Secure the CLEARPOINT
®
V against shifting on the load platform or fork-lift truck.
Move the CLEARPOINT
®
V to the place of installation.
The function and service life of the CLEARPOINT
®
V depends on the conditions at the place of
installation. This place must meet the following requirements:
The device is installed within a building.
The device must not be operated in explosive or fire-endangered atmospheres, in an
environment with aggressive chemicals, superheated steam or strong contamination, or in a very
hot environment.
The CLEARPOINT
®
V must be protected against moisture.
The ambient temperature must not exceed/undercut the indications in the "Technical data"
section.
Choose an even, solid and vibration-free set-up area. The weight of the CLEARPOINT
®
V must
be taken into account when choosing the area.
No vibrations must be transferred to the CLEARPOINT
®
V. If necessary, install the activated-
carbon adsorber on vibration dampers.
The pipework must be free from mechanical stress (otherwise risk of bursting).
It must be ensured that vibrations from other plant components cannot be transferred. This also
and particularly concerns the pulsation of the compressed air as otherwise, the activated carbon
may be destroyed.
Set up the CLEARPOINT
®
V in such a manner that the plant is easily accessible from the sides.
For checks of the pressure vessels, maintenance and repair measures, sufficient free space
must be available on all sides (at least 1.5 m) around the CLEARPOINT
®
V.
Install the activated-carbon adsorber in such a manner that the front panel with the manometer is
well accessible.
The activated-carbon adsorber must be fixed on the floor area by means of the bores in the
frames or feet. In particular as far as devices without a frame construction are concerned, the
tank needs to be secured against tilting at the intended place of installation. In the further course
of the installation, the pipes and dust filters (not included in the scope of delivery) must be fixed
separately, if required.
Ensure sufficient ventilation and heat removal.
Keep a safe distance from transport routes when setting up the CLEARPOINT
®
V.
Equip the plant with a suitable collision guard.
In the event of doubt, we recommend obtaining expert advice regarding the place of installation.
Remove the packaging of the CLEARPOINT
®
V.
Move the CLEARPOINT
®
V to the place of installation.
Position the CLEARPOINT
®
V at the desired place and adjust the plant accordingly.