Maintenance
CLEARPOINT® L 205 – L295 V
45
5.
Mount the fill plug with a seal at the filler neck of the container. As regards the CLEARPOINT
®
L 205
V, mount the compressed-air distributor and then re-establish the connection to the pipework.
6.
Check the connections for tightness. In this respect, follow the directions in the "Initial start-up"
section.
16.4 Periodic inspections
The pressure vessel of the CLEARPOINT
®
V activated-carbon adsorber must be checked at regular
intervals by a technical expert or an authorised expert. The determination of the time limits regarding
periodic inspections is incumbent on the operator and, depending on the classification into the pressure
device category in accordance with the Pressure Equipment Directive, must be carried out by a certified
inspection agency.