WHAT’S INCLUDED

The major components for the brick oven are shown in Figures 1 and 2. Figure 1 shows the top 
unit of the brick oven. Figure 2 shows the base unit of the brick oven. Figure 2 also shows the filler 
blocks or “plugs” that are used to fill the fork slots on the base unit. Eight plugs are shipped with 
each brick oven. Plugs may need to be shaved down to get a proper fit.

- 3 -

FIGURE 1  -  TOP

FIGURE 2  -  BASE

B

B

B

B

Summary of Contents for ELEMENTS OUTDOOR LIVING BRISTOL

Page 1: ...ELEMENTS OUTDOOR LIVING BRISTOL BRICK OVEN INSTALLATION MANUAL BELGARD COM ...

Page 2: ...l building code requirements in your area Brick ovens typically have a minimum setback from all buildings It is also necessary to construct a properly compacted gravel base to set the brick oven on Before construction of the gravel pad it is necessary to establish Finish Grade height first to ensure the first course of the brick oven unit is buried 4 Once finished height has been determined constr...

Page 3: ...p unit of the brick oven Figure 2 shows the base unit of the brick oven Figure 2 also shows the filler blocks or plugs that are used to fill the fork slots on the base unit Eight plugs are shipped with each brick oven Plugs may need to be shaved down to get a proper fit 3 FIGURE 1 TOP FIGURE 2 BASE B B B B ...

Page 4: ... until transported to final install location then remove from pallet and place on foundation 5 DO NOT place the entire brick oven on an uneven footing 6 DO check with local building codes Not following these guidelines can result or lead to equipment damage and or serious injury IMPORTANT When unloading moving or setting a modular unit be sure that the unit is securely strapped using a 5 000 lb st...

Page 5: ...table enough for support of the Elements structure The graded aggregate base material should not be placed directly on topsoil or other organic soils If the exposed soils are too soft to work with the excavation depth may need to be extended or an alternative foundation support system may be necessary Level and compact the exposed excavation base until it is firm and unyielding Once the excavation...

Page 6: ...een established is to place the base unit Remember the first 4 are always buried After the base unit has been placed you can now place the brick oven top 6 BASE UNIT TOP UNIT NOTE Top of brick oven must be installed from the backside due to construction of the pieces ...

Page 7: ...n base and top you will find a set of plugs that are used to fill the fork slots on the units Push the plugs in slowly until they are flush with the blocks next to them It is not necessary to glue them in place 7 B PLUGS A PLUG A PLUG A PLUG A PLUG B PLUGS ...

Page 8: ...d height has been determined construction of the concrete pad can be completed FIGURE B Sample framework for concrete pad FIGURE C Sample side view of completed concrete pad FIGURE B C A properly constructed level footing is required to place your bottom unit on If you are unfamiliar with soil conditions and the process of pouring a concrete footing please consult a professional masonry contractor...

Page 9: ... 9 NOTES ...